NextDecade Corporation
Loading chart...
Item 1. Business
Company Overview and Formation
NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG. We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”). The first five liquefaction trains and related infrastructure (together, "Phase 1", "Train 4", and "Train 5") at the Rio Grande LNG Facility are currently under construction. We are also developing and advancing the permitting process for expansion Trains 6 through 8 and exploring a potential carbon capture and storage ("CCS") project at the Rio Grande LNG Facility.
We are focused on constructing and operating the Rio Grande LNG Facility safely, efficiently, on schedule, and on budget. We seek to deliver secure, affordable, and cleaner energy through the development and operation of liquefaction capacity at the Rio Grande LNG Facility.
We were incorporated in Delaware on May 21, 2014, and were formed for the purpose of acquiring, through a merger, share exchange, asset acquisition, stock purchase, recapitalization, reorganization, or other similar business combination, one or more businesses or entities. On July 24, 2017, one of our subsidiaries merged with and into NextDecade LLC, an LNG development company founded in 2010 to develop LNG export projects and associated pipelines. Prior to the merger with NextDecade LLC, we had no operations and our assets consisted of cash proceeds received in connection with our initial public offering.
Our common stock trades on the Nasdaq Capital Market (“Nasdaq”) under the symbol “NEXT.”
Rio Grande LNG Facility Activity
Liquefaction Facilities Overview
We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on approximately 1,000 acres of land which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast, access to a large, skilled local labor force, and strong geotechnical conditions requiring less piling for soil stabilization. Trains 1 through 5 at the Rio Grande LNG Facility are under construction, and we are developing and advancing the permitting process for Trains 6 through 8. There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.
Construction commenced on Phase 1 at the Rio Grande LNG Facility in July 2023, on Train 4 in September 2025, and on Train 5 in October 2025, in each case following a positive final investment decision ("FID") and the closing of project financing by the Company's subsidiaries. Construction will be completed by Bechtel Energy Inc. (“Bechtel”) under fully wrapped, lump-sum turnkey engineering, procurement, and construction (“EPC”) contracts, and the facility will utilize Honeywell AP-C3MR liquefaction technology, which is a predominant liquefaction technology utilized globally.
The combined scope of Phase 1, Train 4, and Train 5 includes five liquefaction trains with a total expected LNG production capacity of approximately 30 million tonnes per annum ("MTPA"), four 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, ground flares, roads, levees surrounding the site, and warehouses, administrative, operations control room, and maintenance buildings.
LNG Sale and Purchase Agreements for Trains 1 through 5
We have entered into long-term LNG Sale and Purchase Agreements ("SPAs") with 14 creditworthy counterparties for aggregate volumes of approximately 25.3 MTPA of LNG from Trains 1 through 5 at the Rio Grande LNG Facility. The SPAs have a weighted average term of 19.5 years. Under these SPAs, the customers will purchase LNG from the Rio Grande LNG Facility for a price consisting of a fixed fee per MMBtu of LNG plus a variable fee per MMBtu of LNG, with the variable fees structured to cover the expected cost of natural gas plus fuel and other sourcing costs to produce LNG. In certain circumstances, customers may elect to cancel or suspend deliveries of LNG cargoes, in which case the customers would still be required to pay the fixed fee with respect to cargoes that are not delivered. A portion of the fixed fee under each SPA will be subject to annual adjustment for inflation. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific train; however, the commencement of the term of each SPA is tied to a specified train.
Each of these SPAs is currently effective, and deliveries of LNG under these SPAs will commence on the respective Date of First Commercial Delivery (“DFCD”), which is primarily tied to the substantial completion or guaranteed substantial completion dates of specific trains as defined in each SPA. Of the SPAs for Trains 1 through 5, approximately 23.75 MTPA are linked to Henry Hub and have average fixed fees, unadjusted for inflation, totaling approximately $3.0 billion expected to be paid annually.
Marketing of Uncontracted Volumes
We expect to sell any commissioning LNG volumes and operational LNG volumes in excess of SPA volumes ("portfolio volumes") into the LNG market through spot, short-term, and medium-term agreements. We have entered into certain time charter agreements and expect to enter into additional time charter agreements with vessel owners to provide shipping capacity for LNG sales
7
related to our 1.0 MTPA delivered ex-ship SPA, expected commissioning volumes, and expected portfolio volumes. We may subcharter vessels with third parties from time to time to manage our shipping needs relative to chartered capacity.
Engineering, Procurement and Construction (“EPC”)
We have entered into fully wrapped, lump-sum turnkey contracts with Bechtel, a well-established and reputable LNG engineering and construction firm, for the engineering, procurement, and construction of Phase 1, Train 4, and Train 5 at the Rio Grande LNG Facility, under which Bechtel has generally guaranteed cost, performance, and schedule. Under these EPC contracts, Bechtel is responsible for the engineering, procurement, construction, commissioning, and startup of liquefaction trains and their respective related infrastructure.
On July 12, 2023, we issued final notice to proceed to Bechtel under the EPC contracts for Phase 1. Total expected capital costs for Phase 1 are estimated to be approximately $18.0 billion, including estimated EPC costs, owner’s costs, contingencies, and financing costs, and including amounts spent prior to FID under limited notices to proceed.
On September 9, 2025, we issued final notice to proceed to Bechtel under the EPC contract for Train 4. Total expected capital costs for Train 4 are estimated to be approximately $6.7 billion, including estimated EPC costs, owner's costs, contingencies, financing costs, and other costs, including a payment to be made at the commencement of operations to the trains in commercial operation at such date for Train 4's proportionate share of the capital costs of the common facilities it will access, net of the capital cost of any common facilities constructed under the Train 4 EPC contract.
On October 16, 2025, we issued final notice to proceed to Bechtel under the EPC contract for Train 5. Total expected capital costs for Train 5 are estimated to be approximately $6.7 billion, including estimated EPC costs, owner's costs, contingencies, financing costs, and other costs, including a payment to be made at the commencement of operations to the trains in commercial operation at such date for Train 5's proportionate share of the capital costs of the common facilities it will access, net of the capital cost of any common facilities constructed under the Train 5 EPC contract.
Natural Gas Transportation and Supply
We are in the process of executing a substantial and diversified natural gas feedstock sourcing and transportation strategy to spread risk exposure across multiple contracts, counterparties, and pricing hubs. We expect to enter into gas supply arrangements with a wide range of suppliers, and we also expect to leverage trading platforms and exchanges to lock in natural gas supply prices and/or hedge risk.
We have entered into agreements for transportation of natural gas to the Rio Grande LNG Facility on both a firm and interruptible basis to support commissioning and operations and provide the ability to purchase natural gas supplies at the Agua Dulce Hub and other physical access points, giving us access to prolific gas production from the Permian Basin, Eagle Ford Shale, and additional basins, and providing significant flexibility to obtain competitively priced natural gas feedstock.
We believe our proximity to major reserve basins and shale plays, increasing pipeline capacity in the area, a significant amount of natural gas production and infrastructure investment, as well as our existing contacts and discussions with some of the largest regional operators, represent key elements of a comprehensive and effective feed gas strategy.
NextDecade Economic Interest in Trains 1 Through 5
Pursuant to a joint venture agreement with equity partners for ownership of Phase 1 at the Rio Grande LNG Facility, we expect to receive up to approximately 20.8% of distributions of available cash generated from Phase 1 operations, provided that a majority of the cash distributions to which we are otherwise entitled will be paid for any distribution period only after our equity partners receive an agreed distribution threshold in respect of such distribution period and certain other deficit payments from prior distribution periods, if any, are made.
Pursuant to a joint venture agreement with equity partners for ownership of Train 4 at the Rio Grande LNG Facility, we expect to receive 40% of distributions of available cash generated from Train 4 operations, which will increase to 60% when the equity partners receive a certain return on their investments in Train 4.
Pursuant to a joint venture agreement with equity partners for ownership of Train 5 at the Rio Grande LNG Facility, we expect to receive 50% of distributions of available cash generated from Train 5 operations, which will increase to 70% when the equity partners receive a certain return on their investments in Train 5.
Development of Additional Liquefaction Capacity
We are developing and advancing the permitting process for Trains 6 through 8 at the Rio Grande LNG Facility site, which are currently wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. In November 2025, we initiated the pre-filing process with FERC for expansion at the Rio Grande LNG Facility that includes Train 6 and
8
an additional marine berth, and we expect to file a full application for this expansion with FERC in mid-2026. We are evaluating multiple areas on the site for the development of Trains 7 and 8 and expect to advance the development of these trains throughout 2026.
There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.
Governmental Permits, Approvals and Authorizations
We are required to obtain governmental approvals and authorizations to implement our proposed business strategy, which includes the design, construction and operation of the Rio Grande LNG Facility and the export of LNG from the U.S. to foreign countries. The design, siting, construction and operation of LNG export facilities and the export of LNG is a regulated activity and is subject to Section 3 of the Natural Gas Act (the "NGA"). Federal law has bifurcated regulatory jurisdiction of LNG export activities. The Federal Energy Regulatory Commission ("FERC") has jurisdiction to authorize the siting, construction and operation of LNG export facilities. The Department of Energy (“DOE”) has jurisdiction over the import and export of the natural gas commodity, including natural gas in the form of LNG. The FERC also has jurisdiction over the siting, construction and operation of interstate natural gas pipelines under Section 7 of the NGA and regulates interstate pipelines’ rates and terms and conditions of service under Sections 4 and 5 of the NGA. In 2002, the FERC established a policy of not regulating the terms and conditions of service for LNG import or export facilities or requiring that LNG import or export facilities operate as “open access” facilities for all customers. The Energy Policy Act of 2005, which amended the NGA, codified this policy until January 1, 2015, and the FERC has not indicated that it intends to depart from its policy of not regulating the terms or conditions of service or requiring that LNG import or export facilities operate on an open access basis.
Although the FERC acts as the lead agency with jurisdiction over LNG import and export facilities, other federal and state agencies act as cooperating agencies, coordinating with the FERC to evaluate applications for LNG export facilities. These agencies include the U.S. Department of Transportation’s Pipeline and Hazardous Materials Safety Administration (the “PHMSA”), the U.S. Coast Guard (the “Coast Guard”), the U.S. Army Corps of Engineers, the U.S. Environmental Protection Agency, the International Boundary and Water Commission and other federal agencies with jurisdiction over potential environmental impacts of LNG export facility construction and operation. Certain federal laws, such as the Clean Water Act, the Clean Air Act and the Coastal Zone Management Act, delegate authority over certain actions to state agencies, like the Texas Commission on Environmental Quality and the Railroad Commission of Texas. In reviewing an application for an LNG import or export facility or an interstate natural gas pipeline, the FERC also works with these state agencies that have jurisdiction over certain aspects of LNG facility or interstate natural gas pipeline construction or operation.
In particular, the PHMSA has established safety standards for interstate natural gas pipelines and LNG facilities. Similarly, the Coast Guard has established safety regulations for marine operations at LNG facilities and the operation of LNG carriers. The FERC, the PHMSA and the Coast Guard entered into a Memorandum of Understanding in 2004 that establishes the FERC’s primary role in evaluating LNG facility applications and defines the process for coordinating the review of an LNG import or export facility application with the PHMSA and the Coast Guard. In 2018, the FERC and the PHMSA entered into a separate Memorandum of Understanding that establishes the process and timeline by which the PHMSA should determine whether an LNG facility will meet the PHMSA’s LNG safety siting standards.
We have obtained all major permits required to build and export LNG from the first five liquefaction trains and related infrastructure at the Rio Grande LNG Facility, including FERC approval and Department of Energy FTA and non-FTA export authorizations.
In March 2025, the U.S. Court of Appeals for the District of Columbia (the "D.C. Circuit Court") issued a revision to its August 2024 decision regarding our FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC was to consider the issue of a supplemental Environmental Impact Statement (“SEIS”) in view of several executive orders issued since January 20, 2025.
In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. In August 2025, the FERC issued a final order on remand (“Remand Order”) reaffirming its authorization for the siting, construction, and operation of the first five liquefaction trains at the Rio Grande LNG Facility. In September 2025, a request for rehearing of the Remand Order was filed by certain intervenors and on October 30, 2025, the rehearing request was deemed denied by operation of law, rendering the Remand Order no longer appealable to FERC. In December 2025, the intervenors that filed a request for rehearing with FERC petitioned the D.C. Circuit Court to review the Remand Order, and their request remains pending.
Corporate and Other Activities
We are required to maintain corporate and general and administrative functions to serve our business activities described above, including construction of Trains 1 through 5 at the Rio Grande LNG Facility, the development of Trains 6 through 8, and evaluating the potential development of a CCS project at the Rio Grande LNG Facility.
Competition
We are subject to a high degree of competition in all aspects of our business. See “Item 1.A — Risk Factors — Competition in the industries in which we operate is intense, and some of our competitors have greater financial, technological and other resources.”
The Rio Grande LNG Facility will compete with liquefaction facilities worldwide to supply LNG to the global market. In this market, we will compete with a variety of companies, such as independent, technology-driven companies, state-owned companies, and other independent oil and natural gas companies and utilities. Many of these competitors have longer operating histories, more
9
development experience, greater name recognition, greater access to the LNG market, more employees, and substantially greater financial, technical and marketing resources than we currently possess.
Employees
As of December 31, 2025, we had 360 full-time employees. We have no collective bargaining agreements with our employees.
Offices
Loading financial statements...
Financial statements
data from SEC XBRL filings. Values are as-reported; restatements supersede originals. Values reported in .
| Line item |
|---|
| Period ending |
Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations
Forward-Looking Statements
This Quarterly Report on Form 10-Q contains certain statements that are, or may be deemed to be, "forward-looking statements" within the meaning of Section 27A of the Securities Act of 1933, as amended (the “Securities Act”), and Section 21E of the Securities Exchange Act of 1934, as amended (the “Exchange Act”). All statements other than statements of historical fact contained in this Quarterly Report on Form 10-Q, including statements regarding our future results of operations and financial position, strategy and plans, and our expectations for future operations and economic performance, are forward-looking statements. The words “anticipate,” “contemplate,” “estimate,” “expect,” “project,” “plan,” “intend,” “believe,” “seek,” “may,” “might,” “will,” “would,” “could,” “should,” “can have,” “likely,” “continue,” “design,” “assume,” “budget,” “forecast,” “target,” and other words and terms of similar expressions are intended to identify forward-looking statements.
We have based these forward-looking statements on assumptions and analysis made by us in light of our current expectations, perceptions of historical trends, current conditions and projections about future events and trends that we believe may affect our financial condition, results of operations, strategy, short-term and long-term business operations and objectives and financial needs.
Although we believe that the expectations reflected in our forward-looking statements are reasonable, actual results could differ from those expressed in our forward-looking statements. Our future financial position and results of operations, as well as any forward-looking statements, are subject to change and inherent risks and uncertainties, including those described in the section titled “Risk Factors” in our most recent Annual Report on Form 10-K as supplemented by Item 1A of this Quarterly Report on Form 10-Q. You should consider our forward-looking statements in light of a number of factors that may cause actual results to vary from our forward-looking statements including, but not limited to:
•our progress in the development of our natural gas liquefaction and liquefied natural gas (“LNG”) export project and the timing of that progress;
•the timing and cost of the development, construction and operation of the first five liquefaction trains and related common facilities of the multi-plant integrated natural gas liquefaction and LNG export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”);
•the availability and frequency of cash distributions available to us from the Joint Ventures, which own Phase 1, Train 4, and Train 5 of the Rio Grande LNG Facility;
•the timing and cost of the development of subsequent liquefaction trains at the Rio Grande LNG Facility;
•the ability to generate sufficient cash flow to satisfy our and our subsidiaries’ significant debt service obligations or to refinance such obligations ahead of their maturity;
•restrictions imposed by our or our subsidiaries’ debt agreements that limit flexibility in operating our business;
•increases in interest rates increasing the cost of servicing indebtedness;
•our reliance on third parties to successfully complete the Rio Grande LNG Facility and related pipelines and other infrastructure;
•our ability to secure additional debt and equity financing in the future, including any refinancing of outstanding indebtedness, on commercially acceptable terms;
•the accuracy of estimated costs for the Rio Grande LNG Facility;
•our ability to achieve operational characteristics of the Rio Grande LNG Facility, when completed, including LNG production capacity, and any differences in such operational characteristics from our expectations;
•the development risks, operational hazards, and regulatory approvals applicable to the Rio Grande LNG Facility and our LNG and construction and operation activities, and those of our third-party contractors and counterparties;
•the ability to obtain or maintain governmental approvals to construct or operate the Rio Grande LNG Facility;
•technological innovation which may lessen our anticipated competitive advantage or demand for our offerings;
•the global demand for and price of LNG;
•the availability of LNG vessels worldwide;
•changes in legislation and regulations relating to the LNG industry, including environmental laws and regulations that impose significant compliance costs and liabilities;
•global pandemics, the Russia-Ukraine conflict, conflicts in the Middle East, other sources of volatility in the energy markets and their impact on our business and operating results, including any disruptions in our operations or development of the Rio Grande LNG Facility and the health and safety of our employees, and on our customers, the global economy and the demand for LNG;
•risks related to doing business in and having counterparties in foreign countries, including as a result of tariffs;
14
•our ability to maintain the listing of our securities on the Nasdaq Capital Market or another securities exchange or quotation medium;
•changes adversely affecting the businesses in which we are engaged;
•management of growth;
•general economic conditions, including inflation and rising interest rates;
•our ability to generate cash; and
•the result of future financing efforts and applications for customary tax incentives.
Should one or more of the foregoing risks or uncertainties materialize in a way that negatively impacts us, or should the assumptions underlying our forward-looking statements prove incorrect, our actual results may vary materially from those anticipated in our forward-looking statements, and our business, financial condition, and results of operations could be materially and adversely affected.
The forward-looking statements contained in this Quarterly Report on Form 10-Q are made as of the date of this Quarterly Report on Form 10-Q. You should not rely upon forward-looking statements as predictions of future events. In addition, neither we nor any other person assumes responsibility for the accuracy and completeness of any of these forward-looking statements. Except as required by applicable law, we do not undertake any obligation to publicly correct or update any forward-looking statement.
All forward-looking statements attributable to us are expressly qualified in their entirety by these cautionary statements as well as others made in our most recent Annual Report on Form 10-K as well as other filings we have made and will make with the Securities and Exchange Commission (the “SEC”) and our public communications. You should evaluate all forward-looking statements made by us in the context of these risks and uncertainties.
Overview of Business and Significant Developments
Overview of Business
NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG. We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”). The first five liquefaction trains and related infrastructure (together, “Phase 1”, “Train 4”, and “Train 5”) at the Rio Grande LNG Facility are currently under construction. We are also developing and advancing the permitting process for expansion Trains 6 through 8 at the Rio Grande LNG Facility.
We are focused on constructing and operating the Rio Grande LNG Facility safely, efficiently, on schedule, and on budget. We seek to deliver secure, affordable, and cleaner energy through the development and operation of liquefaction capacity at the Rio Grande LNG Facility.
Significant Recent Developments
Significant developments since January 1, 2026, include the following:
Construction and Commissioning
•Progress on Trains 1 through 5 under the engineering, procurement, and construction (“EPC”) contracts with Bechtel Energy, Inc. (“Bechtel”) as of September 2026 consisted of:
| Overall Completion Percentage | Engineering | Procurement | Construction | Commissioning | |||||||||||||
| Trains 1 and 2 | 79.7% | 99.5% | 99.6% | 68.8% | 4.9% | ||||||||||||
| Train 3 | 55.2% | 97.7% | 93.1% | 24.5% | — | ||||||||||||
| Train 4 | 22.5% | 82.9% | 39.2% | 2.8% | — | ||||||||||||
| Train 5 | 14.0% | 47.4% | 26.8% | 0.5% | — |
•During the second quarter of 2026, we safely energized our main substation with 138kV power in May, and we seconded over 100 operational employees to Bechtel in June as part of preparations for first LNG production.
•During the third quarter of 2026, construction of Phase 1 at the Rio Grande LNG Facility continued to progress safely, on budget, and ahead of schedule, with Train 1 electrical, mechanical, and utility commissioning scopes progressing and installation of the Train 2 main cryogenic heat exchanger completed. Dredging activities for the berths, turning basin, and channel deepening were completed. The gas inlet facilities achieved ready for start-up, and the Bay Runner pipeline reached in-service. We continue to expect first gas into the Rio Grande LNG Facility before year-end 2026.
•We expect first LNG production from Train 1 at the Rio Grande LNG Facility in the second quarter of 2027 and substantial completion of Train 1 in the third quarter of 2027, which is a quarter ahead of the guaranteed completion schedule under the EPC contract with Bechtel.
15
Development
•In May 2026, we filed a formal application with the Federal Energy Regulatory Commission (“FERC”) for expansion at the Rio Grande LNG Facility that includes Train 6 and an additional marine berth. With the application, we requested a waiver from FERC of the approximately one month remaining in the Train 6 pre-filing period, and FERC granted that waiver in June 2026.
•In June 2026, we filed an application with the Department of Energy for LNG export authorizations for Train 6.
•In June 2026, we executed a Reservation Agreement with Baker Hughes for the supply of main refrigeration compressors for Train 6.
•In July 2026, FERC issued its schedule of environmental review for Train 6 at the Rio Grande LNG Facility, and the final Environmental Impact Statement is expected in June 2027.
•In September 2026, we received permit authorization from the U.S. Army Corps of Engineers (“USACE”) for Train 6, completing a key regulatory authorization required for construction.
•In September 2026, FERC approved our uprate request for the Rio Grande LNG Facility, increasing the authorized liquefaction capacity of the first five trains at the Rio Grande LNG Facility to 30.15 million tonnes per annum (“MTPA”).
Strategic and Commercial
◦In early 2026, we began the marketing of early cargoes that we expect to produce prior to the commencement of our long-term LNG Sale and Purchase Agreements (“SPAs”). In February 2026, we entered into LNG sales agreements for the sale of over 175 TBtu of LNG on a free-on-board (“FOB”) basis, with fixed liquefaction fees that are expected to achieve a cargo margin, calculated as the FOB LNG sales price less our expected costs of natural gas feedstock and fuel, of over $3.00 per MMBtu. This volume represents approximately 33% of our expected portfolio volumes from 2027 through early 2029.
Financial
◦In April 2026, Rio Grande LNG Train 5, LLC issued a second installment of $100.0 million and in July 2026 issued a third installment of $100.0 million of 6.56% Senior Secured Notes due in 2050, pursuant to the Note Purchase Agreement entered into in conjunction with the positive final investment decision (“FID”) on Train 5 in October 2025, for the issuance of $500.0 million aggregate senior secured notes.
◦In June 2026, Rio Grande LNG Intermediate HoldCo Borrower, LLC (“Phase 1 HoldCo Borrower”) entered into a credit agreement for a $1.0 billion term loan which bears interest at 7.05%, payable in cash or in-kind at our election until the first interest payment date after June 2029 and in cash thereafter, and matures in June 2033. Net proceeds from this term loan were used to reduce outstanding borrowings under the Rio Grande LNG, LLC (“Phase 1 LLC”) credit facilities, to pay fees and expenses associated with the transaction, and to pay general and administrative expenses of Phase 1 HoldCo Borrower.
◦In July 2026, Phase 1 LLC completed an offering of $3.5 billion aggregate principal amount of senior secured notes. The net proceeds from the offering were used to repay approximately $3.5 billion of outstanding borrowings under the Phase 1 LLC credit facilities and to pay fees and expenses associated with the transaction. The tranches of senior secured notes issued were:
▪$1.0 billion aggregate principal amount of senior secured notes due 2031, which bear interest at 5.25% and will mature in June 2031,
▪$500.0 million aggregate principal amount of senior secured notes due 2034, which bear interest at 5.50% and will mature in January 2034,
▪$1.25 billion aggregate principal amount of senior secured notes due 2036, which bear interest at 5.75% and will mature in June 2036, and
▪$750.0 million aggregate principal amount of senior secured notes due 2041, which bear interest at 6.15% and will mature in June 2041.
◦In conjunction with the Phase 1 HoldCo Borrower credit agreement and the Phase 1 LLC senior secured notes offering and repayment of credit facility borrowings as a result of those transactions, Phase 1 LLC also reduced the notional amount of certain of its interest rate swaps, resulting in settlement receipts totaling approximately $109.2 million in July 2026. These settlement receipts were used to reduce outstanding borrowings under the Phase 1 LLC credit facilities.
◦In September 2026, Phase 1 LLC issued $575.0 million of senior secured notes in a private placement, which bear interest at 6.72% and will amortize over a period of approximately 18.5 years beginning in June 2029, with a final maturity in December 2047. Proceeds were used to reduce outstanding borrowings under the Phase 1 LLC credit facilities and to pay fees and expenses associated with the transaction.
◦In October 2026, Rio Grande LNG Train 5, LLC issued the final installment of $150.0 million of 6.56% Senior Secured Notes due in 2050, pursuant to the Note Purchase Agreement entered into in conjunction with the positive FID on Train 5 in October 2025 for the issuance of $500.0 million aggregate senior secured notes, which are now fully issued and outstanding.
16
Rio Grande LNG Facility Activity
Liquefaction Facilities Overview and Construction Progress
We are constructing and developing the Rio Grande LNG Facility which is located in the Rio Grande Valley near Brownsville, Texas. The site is located on approximately 1,000 acres of land, which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian Basin and Eagle Ford Shale, location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast, access to an uncongested waterway for vessel loading, access to a large, skilled local labor force, and strong geotechnical conditions requiring less piling for soil stabilization than liquefaction facilities in other areas of the U.S. Gulf Coast. Trains 1 through 5 at the Rio Grande LNG Facility are under construction, and we are developing and advancing the permitting process for Trains 6 through 8. There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.
Construction commenced on Phase 1 at the Rio Grande LNG Facility in July 2023, on Train 4 in September 2025, and on Train 5 in October 2025, in each case following a positive FID and the closing of project financing by the Company’s subsidiaries. Construction will be completed by Bechtel under fully wrapped, lump-sum turnkey EPC contracts, and the liquefaction trains will utilize Honeywell AP-C3MR liquefaction technology, which is a predominant liquefaction technology utilized globally.
The combined scope of Phase 1, Train 4, and Train 5 includes five liquefaction trains with a total expected LNG production capacity of 30 MTPA, four 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, ground flares, roads, levees surrounding the entire site, warehouses, and operations control room, maintenance, and administrative buildings.
Progress on Phase 1 as of September 2026 is ahead of the guaranteed completion schedule under the EPC contracts. Train 1 electrical, mechanical, and utility commissioning scopes are progressing. Installation and pre-alignment of the Train 2 compressor strings was completed, and the Train 2 main cryogenic heat exchanger was installed. The first compressor string was set for Train 3. Inner nickel plate welding and the first hydrotest were completed for Tank 1.
Progress on Trains 4 and 5 as of September 2026 is in line with the guaranteed completion schedule under the EPC contracts. Foundation pours for the Train 4 main cryogenic rack began, and excavation of the Train 4 refrigeration area commenced. Train 5 soil stabilization via the direct mixing method process began. Tank 3 piling work progressed, and piling began for Tank 4.
Dredging activities for the berths, turning basin, and channel deepening were completed. The gas inlet facilities have achieved ready for start-up, the Bay Runner pipeline reached in-service during the third quarter of 2026, and across the site there is ongoing commissioning of systems to support initial hydrocarbon introduction before year-end 2026.
LNG Sale and Purchase Agreements for Trains 1 Through 5
We have entered into long-term LNG SPAs with 14 creditworthy counterparties for aggregate volumes of approximately 25.3 MTPA of LNG from Trains 1 through 5 at the Rio Grande LNG Facility. The SPAs have a weighted average term of 19.5 years. Under these SPAs, the customers will purchase LNG from the Rio Grande LNG Facility for a price consisting of a fixed fee per MMBtu of LNG plus a variable fee per MMBtu of LNG, with the variable fees structured to cover the expected cost of natural gas plus fuel and other sourcing costs to produce LNG. In certain circumstances, customers may elect to cancel or suspend deliveries of LNG cargoes, in which case the customers would still be required to pay the fixed fee with respect to cargoes that are not delivered. A portion of the fixed fee under each SPA will be subject to annual adjustment for inflation. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific train; however, the commencement of the term of each SPA is tied to a specified train.
Each of these SPAs is currently effective, and deliveries of LNG under these SPAs will commence on the respective Date of First Commercial Delivery (“DFCD”), which is primarily tied to the substantial completion or guaranteed substantial completion dates of specific trains as defined in each SPA. Of the approximately 25.3 MTPA of SPAs for Trains 1 through 5, 23.75 MTPA are linked to Henry Hub and have average fixed fees, unadjusted for inflation, totaling approximately $3.0 billion expected to be paid annually.
Marketing of Uncontracted Volumes
We expect to sell any commissioning LNG volumes and operational LNG volumes in excess of SPA volumes (“portfolio volumes”) into the LNG market through spot, short-term, and medium-term agreements. We have entered into certain time charter agreements and expect to enter into additional time charter agreements with vessel owners to provide shipping capacity for commissioning and operational volumes. We have also entered into certain subcharter agreements and may enter into additional subcharter agreements with third parties from time to time to manage our LNG shipping needs relative to chartered capacity.
Engineering, Procurement, and Construction (“EPC”)
We have entered into fully wrapped, lump-sum turnkey contracts with Bechtel, a well-established and reputable LNG engineering and construction firm, for the engineering, procurement, and construction of Phase 1, Train 4, and Train 5 at the Rio Grande LNG Facility, under which Bechtel has generally guaranteed cost, performance, and schedule. Under these EPC contracts, Bechtel is responsible for the engineering, procurement, construction, commissioning, and startup of liquefaction trains and their respective related infrastructure.
17
On July 12, 2023, we issued final notice to proceed to Bechtel under the EPC contracts for Phase 1. Total expected capital costs for Phase 1 are estimated to be approximately $18.0 billion, including estimated EPC costs, owner’s costs, contingencies, and financing costs, and including amounts spent prior to FID under limited notices to proceed.
On September 9, 2025, we issued final notice to proceed to Bechtel under the EPC contract for Train 4. Total expected capital costs for Train 4 are estimated to be approximately $6.7 billion, including estimated EPC costs, owner’s costs, contingencies, financing costs, and other costs, including a payment to be made at the commencement of operations to the trains in commercial operation at such date for Train 4’s proportionate share of the capital costs of the common facilities it will access, net of the capital cost of any common facilities constructed under the Train 4 EPC contract.
On October 16, 2025, we issued final notice to proceed to Bechtel under the EPC contract for Train 5. Total expected capital costs for Train 5 are estimated to be approximately $6.7 billion, including estimated EPC costs, owner’s costs, contingencies, financing costs, and other costs, including a payment to be made at the commencement of operations to the trains in commercial operation at such date for Train 5’s proportionate share of the capital costs of the common facilities it will access, net of the capital cost of any common facilities constructed under the Train 5 EPC contract.
Natural Gas Transportation and Supply
We are in the process of executing a substantial and diversified natural gas feedstock sourcing and transportation strategy to spread risk exposure across multiple contracts, counterparties, and pricing hubs. We have entered into and expect to enter into additional gas supply arrangements with a wide range of suppliers, and we also expect to leverage trading platforms and exchanges to manage natural gas supply prices and/or hedge risk.
We have entered into agreements for transportation of natural gas to supply the Rio Grande LNG Facility on both a firm and interruptible basis to support commissioning and operations and provide the ability to purchase natural gas supplies at the Agua Dulce Hub and other physical access points, giving us access to prolific gas production from the Permian Basin, Eagle Ford Shale, and additional basins, and providing significant flexibility to obtain competitively priced natural gas feedstock.
We believe our proximity to major reserve basins and shale plays, increasing pipeline capacity in the area, a significant amount of natural gas production and infrastructure investment, as well as our existing contacts and discussions with some of the largest regional operators, represent key elements of a comprehensive and effective feed gas strategy.
NextDecade Economic Interest in Trains 1 Through 5
Pursuant to a joint venture agreement with equity partners for ownership of Phase 1 at the Rio Grande LNG Facility, we expect to receive up to approximately 20.8% of distributions of available cash generated from Phase 1 operations, provided that a majority of the cash distributions to which we are otherwise entitled will be paid for any distribution period only after our equity partners receive an agreed distribution threshold in respect of such distribution period and certain other deficit payments from prior distribution periods, if any, are made.
Pursuant to a joint venture agreement with equity partners for ownership of Train 4 at the Rio Grande LNG Facility, we expect to receive 40% of distributions of available cash generated from Train 4 operations, which will increase to 60% when our equity partners receive a certain return on their investments in Train 4.
Pursuant to a joint venture agreement with equity partners for ownership of Train 5 at the Rio Grande LNG Facility, we expect to receive 50% of distributions of available cash generated from Train 5 operations, which will increase to 70% when our equity partners receive a certain return on their investments in Train 5.
Development of Additional Liquefaction Capacity
We are developing and advancing the permitting process for Trains 6 through 8 at the Rio Grande LNG Facility. These trains are currently wholly owned by NextDecade and are cumulatively expected to increase the Company’s total expected LNG production capacity by 18 MTPA once constructed and placed into operation.
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility and adjacent to Trains 1 through 5. In May 2026, we filed a formal application with FERC for expansion at the Rio Grande LNG Facility that includes Train 6 and an additional marine berth. In July 2026, FERC issued its schedule of environmental review for Train 6, and the final Environmental Impact Statement is expected in June 2027. Commercialization of Train 6 is underway, and we are progressing discussions with high credit quality potential counterparties for long-term agreements for the sale of LNG from Train 6.
We are developing Trains 7 and 8 on the western end of the Rio Grande LNG Facility site and expect to pre-file with FERC for Trains 7 and 8 before year-end 2026.
There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.
Governmental Permits, Approvals, and Authorizations - Trains 1 through 5
We have obtained all major permits required to build and export LNG from the first five liquefaction trains and related infrastructure at the Rio Grande LNG Facility, including FERC approval and Department of Energy FTA and non-FTA authorizations.
In August 2025, FERC issued a final order on remand (“Remand Order”) reaffirming its authorization for the siting, construction, and operation of the first five liquefaction trains at the Rio Grande LNG Facility, following the issuance of a supplemental Environmental Impact Statement in July 2025. In September 2025, certain intervenors filed a request for rehearing of the Remand Order.
18
FERC denied that request by operation of law on October 30, 2025, and issued a substantive order on rehearing in March 2026 that reaffirmed its authorization for the first five liquefaction trains, rendering the Remand Order no longer appealable to FERC. In December 2025, the same intervenors petitioned the D.C. Circuit Court to review the Remand Order, and that appeal remains pending.
In September 2026, FERC approved our uprate request for Trains 1 through 5, increasing the authorized liquefaction capacity of the first five trains at the Rio Grande LNG Facility to 30.15 MTPA.
Governmental Permits, Approvals, and Authorizations - Train 6
In May 2026, we filed a formal application with FERC for expansion at the Rio Grande LNG Facility that includes Train 6 and an additional marine berth. With the application, we requested a waiver from FERC of the approximately one month remaining in the Train 6 pre-filing period, and FERC granted that waiver in June 2026. In July 2026, FERC issued its schedule of environmental review for Train 6 at the Rio Grande LNG Facility, and the final Environmental Impact Statement is expected in June 2027.
In June 2026, we filed an application with the Department of Energy for LNG export authorizations for Train 6.
In September 2026, we received permit authorization from the U.S. Army Corps of Engineers for Train 6, completing a key regulatory authorization required for construction.
Corporate and Other Activities
We are required to maintain corporate and general and administrative functions to serve our business activities described above, including the construction of Trains 1 through 5 and the development of Trains 6 through 8 at the Rio Grande LNG Facility.
Liquidity and Capital Resources
Following FID on Trains 1 through 5 and the project financing obtained by the Company’s subsidiaries, Phase 1 LLC, Train 4 LLC, and Train 5 LLC (together, the “Rio Grande Project Entities”) operate with independent capital structures. Although our sources and uses are presented from a consolidated standpoint, certain restrictions under debt and equity agreements limit the ability of NextDecade and the Rio Grande Project Entities to use and distribute cash. The Rio Grande Project Entities are required to deposit all cash received under their respective debt agreements into restricted accounts. The usage or withdrawal of such cash is restricted to the payment of obligations related to their respective trains and common infrastructure and other restricted payments, and such cash and capital resources are not available to service the obligations of NextDecade.
Phase 1 FID Financing
In connection with the FID on Phase 1 at the Rio Grande LNG Facility in July 2023, Phase 1 LLC obtained approximately $6.2 billion in equity capital commitments, inclusive of commitments from NextDecade, entered into senior secured non-recourse bank credit facilities of $11.6 billion, consisting of $11.1 billion in construction term loans and a $500.0 million working capital facility, and closed a $700.0 million senior secured non-recourse private notes offering. Phase 1 LLC expects to utilize these capital resources to fund the total cost of Phase 1, which is currently estimated at $18.0 billion and consists of EPC costs, owner’s costs and contingencies, dredging for the Brazos Island Harbor Channel Improvement Project, conservation of more than 4,000 acres of wetland and wildlife habitat area, installation of utilities, interest during construction and other financing costs, and including amounts spent prior to FID under limited notices to proceed.
Since July 2023, Phase 1 LLC has refinanced a total of over $7.0 billion of its original $11.1 billion term loan facilities through the issuance of senior secured notes and loans at Phase 1 LLC and a $1.0 billion term loan at Phase 1 HoldCo Borrower.
In April 2025, Phase 1 LLC elected to terminate $250.0 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250.0 million.
Train 4 FID Financing
In connection with the FID on Train 4 at the Rio Grande LNG Facility in September 2025, Train 4 LLC obtained approximately $2.8 billion in equity capital commitments, inclusive of commitments from NextDecade, and entered into a senior secured non-recourse bank credit facility of approximately $3.8 billion. Train 4 LLC expects to utilize these capital resources to fund the total cost of Train 4 and related infrastructure, which is currently estimated at $6.7 billion and consists of EPC costs, owner’s costs and contingencies, interest during construction and other financing costs, and other costs, including a payment for usage of common infrastructure at the Rio Grande LNG Facility.
Train 5 FID Financing
In connection with the FID on Train 5 at the Rio Grande LNG Facility in October 2025, Train 5 LLC obtained approximately $2.6 billion in equity capital commitments, inclusive of commitments from NextDecade, entered into a senior secured non-recourse bank credit facility of approximately $3.6 billion, and closed a $500.0 million senior secured non-recourse private notes offering. Train 5 LLC expects to utilize these capital resources to fund the total cost of Train 5 and related infrastructure, which is currently estimated at $6.7
19
billion and consists of EPC costs, owner’s costs and contingencies, interest during construction and other financing costs, and other costs, including a payment for usage of common infrastructure at the Rio Grande LNG Facility.
Near Term Liquidity and Capital Resources of NextDecade Corporation
Following the respective FIDs of Phase 1, Train 4, and Train 5, costs associated with the EPC agreements, Rio Grande site lease, and other Phase 1, Train 4, and Train 5 related costs are being funded by debt and equity proceeds received by the Rio Grande Project Entities. Our primary corporate cash needs are capital contributions to Trains 4 and 5, development expenses for expansion projects at the Rio Grande LNG Facility, and general and administrative expenses.
In connection with the FIDs of Trains 4 and 5, we committed to make approximately $2.4 billion in equity capital contributions for Train 4 and 5 in the aggregate. At the FIDs of Trains 4 and 5, we used the net proceeds of the Super FinCo $1.2 billion term loans and cash on hand to fund a portion of our equity commitments for Trains 4 and 5. We expect to fund the remainder of our equity commitments to Trains 4 and 5 using borrowings under the FinCo Credit Agreement.
In August 2026, NextDecade LLC, our wholly owned subsidiary and the entity that manages the construction, commissioning, and operation of the Rio Grande LNG Facility on behalf of the Rio Grande Project Entities, received a $50.0 million fee from Train 4 LLC for services rendered by NextDecade LLC in support of Train 4.
Because our businesses and assets are under construction or in development, we have not historically generated significant cash flow from operations, and we do not expect to do so until liquefaction trains at the Rio Grande LNG Facility begin operating. We intend to fund development activities for the foreseeable future with our cash and cash equivalents on hand and through the sale of additional equity, equity-based or debt securities in us or in our subsidiaries. There can be no assurance that we will succeed in selling such securities or, if successful, that the capital we raise will not be expensive or dilutive to stockholders.
Long Term Liquidity and Capital Resources of NextDecade Corporation
We will not receive significant cash flows from liquefaction trains at the Rio Grande LNG Facility until they are operational, and the commercial operation dates for Trains 1 through 5 range from late 2027 for Train 1 through the first half of 2031 for Train 5, based on the guaranteed schedule under the EPC contracts. Any future development of liquefaction trains at the Rio Grande LNG Facility will similarly take an extended period of time to develop, construct, and become operational and will require significant capital deployment.
We currently expect that the long-term capital requirements for future development of liquefaction trains at the Rio Grande LNG Facility will be financed predominantly through the proceeds from future debt, equity-based, and equity offerings by us or our subsidiaries. As a result, our business success will depend, to a significant extent, upon our ability to obtain financing required to fund future development and construction at the Rio Grande LNG Facility, to bring assets into operation on a commercially viable basis, and to finance any required increases in staffing, operating, and expansion costs during that process. There can be no assurance that we will succeed in securing additional debt and/or equity financing in the future to fund future development and construction at the Rio Grande LNG Facility, or, if successful, that the capital we raise will not be expensive or dilutive to stockholders. Additionally, if these types of financing are not available, we will be required to seek alternative sources of financing, which may not be available on terms acceptable to us, if at all.
Sources and Uses of Cash
The following table summarizes the sources and uses of our cash for the periods presented (in thousands):
| Nine Months Ended September 30, | |||||||||||
| 2026 | 2025 | ||||||||||
| Operating cash flows | $ | (16,568) | $ | (148,741) | |||||||
| Investing cash flows | (3,394,211) | (2,880,130) | |||||||||
| Financing cash flows | 3,295,823 | 3,380,783 | |||||||||
| Net (decrease) increase in cash, cash equivalents and restricted cash | (114,956) | 351,912 | |||||||||
| Cash, cash equivalents and restricted cash – beginning of period | 707,088 | 392,762 | |||||||||
| Cash, cash equivalents and restricted cash – end of period | $ | 592,132 | $ | 744,674 | |||||||
Cash used in operating activities for the nine months ended September 30, 2026, decreased by approximately $132.2 million compared to the same period in 2025 primarily due to increased derivative settlements.
Cash used in investing activities for the nine months ended September 30, 2026, increased by approximately $514.1 million compared to the same period in 2025 primarily due to increased expenditures associated with construction of the Rio Grande LNG Facility, including expenditures related to Trains 4 and 5, which achieved positive FIDs and began construction in the second half of 2025.
Cash provided by financing activities for the nine months ended September 30, 2026, decreased by approximately $85.0 million compared to the same period in 2025. The decrease was primarily due to decreases in proceeds from debt issuance, net of debt repayments. The decreases were partially offset by increases in receipts of equity commitments related primarily to construction at the Rio Grande LNG Facility, including impacts of Trains 4 and 5, which achieved positive FIDs in the second half of 2025.
20
Results of Operations
The following table summarizes costs, expenses and other income for the periods indicated (in thousands):
| Three Months Ended September 30, | Nine Months Ended September 30, | |||||||||||||||||||||
| 2026 | 2025 | 2026 | 2025 | |||||||||||||||||||
| Revenues | $ | — | $ | — | $ | — | $ | — | ||||||||||||||
| Operating and maintenance | 13,422 | 15,080 | 51,034 | 48,725 | ||||||||||||||||||
| General and administrative | 48,787 | 53,609 | 111,663 | 122,069 | ||||||||||||||||||
| Development | 2,162 | 2,881 | 7,155 | 4,436 | ||||||||||||||||||
| Depreciation and amortization | 18,541 | 393 | 26,816 | 1,399 | ||||||||||||||||||
| Other | — | — | — | 3,518 | ||||||||||||||||||
| Total operating loss | (82,912) | (71,963) | (196,668) | (180,147) | ||||||||||||||||||
| Other income (expense): | ||||||||||||||||||||||
| Derivative gain (loss), net | 851,229 | (74,141) | 905,194 | (217,684) | ||||||||||||||||||
| Interest expense | (69,260) | (40,279) | (239,284) | (99,119) | ||||||||||||||||||
| Loss on debt extinguishment | (136,511) | — | (168,962) | (9,160) | ||||||||||||||||||
| Other income, net | 11,303 | 1,627 | 18,346 | 5,494 | ||||||||||||||||||
| Income (loss) before income taxes | 573,849 | (184,756) | 318,626 | (500,616) | ||||||||||||||||||
| Income tax expense | — | — | — | — | ||||||||||||||||||
| Net income (loss) | 573,849 | (184,756) | 318,626 | (500,616) | ||||||||||||||||||
| Less: net income (loss) attributable to non-controlling interests | 418,468 | (75,274) | 365,077 | (241,462) | ||||||||||||||||||
| Net income (loss) attributable to common stockholders | $ | 155,381 | $ | (109,482) | $ | (46,451) | $ | (259,154) | ||||||||||||||
Net income (loss) attributable to common stockholders for the three months ended September 30, 2026, increased by approximately $264.9 million compared to the same period in 2025 primarily as a result of the following:
•Depreciation and amortization increased by approximately $18.1 million primarily due to amortization of finance lease right-of-use assets associated with our leases of LNG vessels.
•Derivative gain (loss), net increased by approximately $925.4 million primarily driven by higher forward SOFR rates, which increased the fair-value gain on the Company’s interest rate swap portfolio.
•Interest expense increased by approximately $29.0 million primarily due to additional borrowings to construct the Rio Grande LNG Facility and interest expense associated with our finance leases.
•Loss on debt extinguishment increased by approximately $136.5 million due to repayments made under the CD Credit Agreement and TCF Credit Agreement.
•Other income, net increased by approximately $9.7 million primarily due to income associated with subleases of certain of our LNG vessels under charter to third parties.
•Net income (loss) attributable to non-controlling interests increased by approximately $493.7 million primarily due to changes in interest rate swap derivatives and loss on debt extinguishment recognized within the Joint Ventures’ net income (loss) and consolidated in the Company’s results.
Net income (loss) attributable to common stockholders for the nine months ended September 30, 2026, increased by approximately $212.7 million compared to the same period in 2025 primarily as a result of the following:
•Depreciation and amortization increased by approximately $25.4 million primarily due to amortization of finance lease right-of-use assets associated with our leases of LNG vessels.
•Derivative gain (loss), net increased by approximately $1,122.9 million primarily driven by higher forward SOFR rates, which increased the fair-value gain on the Company’s interest rate swap portfolio.
•Interest expense increased by approximately $140.2 million primarily due to additional borrowings to construct the Rio Grande LNG Facility and interest expense associated with our finance leases.
•Loss on debt extinguishment increased by approximately $159.8 million due to repayments made under the CD Credit Agreement and TCF Credit Agreement.
•Other income, net increased by approximately $12.9 million primarily due to income associated with subleases of certain of our LNG vessels under charter to third parties.
21
•Net income (loss) attributable to non-controlling interests increased by approximately $606.5 million primarily due to changes in interest rate swap derivatives, interest expense, and loss on debt extinguishment recognized within the Joint Ventures’ net income (loss) and consolidated in the Company’s results.
Summary of Critical Accounting Estimates
The preparation of our Consolidated Financial Statements in conformity with GAAP requires management to make certain estimates and assumptions that affect the amounts reported in the Consolidated Financial Statements and the accompanying notes. There were no material changes made by management to the critical accounting estimates in the three months ended September 30, 2026. Please refer to the “Summary of Critical Accounting Estimates” section within “Management’s Discussion and Analysis of Financial Condition and Results of Operations” in our Annual Report on Form 10-K for the year ended December 31, 2025 for a discussion of our critical accounting estimates.
Next expected filings
- ~2027-02-28 10-K expected by 2027-03-06 (in 122 days)
- ~2027-04-28 10-Q expected by 2027-05-01 (in 181 days)
- ~2027-07-27 10-Q expected by 2027-07-30 (in 271 days)
- ~2027-10-26 10-Q expected by 2027-10-29 (in 362 days)
Predicted from historical filing cadence; not an SEC commitment.
Recent SEC filings
- 2026-10-29 10-Q Quarterly Report
- 2026-10-01 8-K Officer/Director Change
- 2026-07-30 10-Q Quarterly Report
- 2026-07-30 S-8 Employee Benefit Plan Registration
- 2026-07-02 8-K Material Agreement Entered; Material Financial Obligation
- 2026-06-18 8-K Material Agreement Entered; Material Financial Obligation
- 2026-06-03 8-K Officer/Director Change
- 2026-05-13 S-3ASR S-3ASR
- 2026-05-01 10-Q Quarterly Report
- 2026-04-23 DEF 14A Proxy Statement
- 2026-04-15 8-K Officer/Director Change
- 2026-03-02 10-K Annual Report
- 2025-11-18 8-K Material Agreement Entered; Material Financial Obligation; Unregistered Equity Sale
- 2025-10-30 10-Q Quarterly Report
- 2025-10-16 8-K Material Agreement Entered; Material Financial Obligation; Officer/Director Change; Regulation FD Disclosure; Other Events; Financial Statements and Exhibits