    ITEM 1.    Business
    Overview
    We are a vertically integrated owner, developer, and operator of large-scale digital infrastructure in the United States, purpose-built to support high-performance computing (“HPC”) workloads, including artificial intelligence (“AI”), machine learning, and advanced cloud applications.
    Our strategy is grounded in controlling infrastructure at utility scale and pairing compute‑optimized facilities with reliable, long‑duration power resources. By controlling land use through ownership or long-term ground leases, together with interconnection rights, electrical and cooling infrastructure, and, where applicable, on-site generation, we deliver resilient, cost-efficient capacity to hyperscale and enterprise customers through long-term hosting arrangements. This infrastructure-first approach enables TeraWulf to serve Tier-1 counterparties while maintaining operational control, development flexibility, and disciplined capital allocation.
    Our platform is differentiated by long-term control of utility-scale infrastructure, deep in-house power and grid expertise, and a scalable development model supported by long-term, credit-enhanced customer contracts.
    HPC Platform and Development Pipeline
    Our contracted HPC platform currently consists of two primary campuses:
    •Lake Mariner Data Campus (the “Lake Mariner Data Campus”), located in Barker, New York within the single-state New York Independent System Operator (“NYISO”) market; and
    •Abernathy HPC Campus (the “Abernathy HPC Campus”), located in Abernathy, Texas, within the Southwest Power Pool (SPP).
    Both campuses have been engineered for phased, large‑scale deployments of liquid‑cooled, hyperscale compute and are supported by long‑term contractual arrangements with credit‑enhanced counterparties. Together, these campuses have contracted 522 MW of critical IT load with long‑dated revenue visibility.
    In addition, the Company holds a long‑term ground lease in Lansing, New York (the “Cayuga Site”), which, upon completion of permitting and site development, has the potential to support up to 400 MW of gross capacity, representing approximately 320 MW of contractual critical IT load. The Cayuga Site provides a third anchor location with existing interconnection and supporting infrastructure and represents a key component of the Company’s forward development pipeline.
    Through a combination of contracted capacity and future expansion opportunities, TeraWulf has established a multi‑regional HPC platform designed to support sustained growth. The Company’s development model targets the contraction of approximately 250 MW to 500 MW of new critical IT HPC capacity annually, aligned with customer demand, power availability, and regional grid conditions.
    Business Strategy
    TeraWulf’s business strategy is focused on the development, ownership, and operation of large‑scale, power‑advantaged digital infrastructure serving hyperscale and enterprise HPC workloads. Our approach is differentiated by:
    •Infrastructure Control and Vertical Integration – We retain majority ownership and direct operational control over core infrastructure assets, including land positions (through ownership or long‑term ground leases), interconnection rights, electrical systems, cooling infrastructure, and, where applicable, on‑site generation. This vertical integration enables disciplined execution, governance oversight, and infrastructure‑style returns.
    1

    •Long‑Term, Credit‑Enhanced Contracting – Our HPC arrangements are structured as long‑term data center leases, typically with base terms ranging from 10 to 25 years, contractual escalators, and renewal and contraction options. Certain projects benefit from investment‑grade credit support, materially strengthening the risk profile and durability of contracted revenues.
    •Scalable, Multi‑Phase Development – Each campus is designed for modular expansion. Initial phases deliver near‑term contracted capacity, while subsequent phases are developed in line with customer deployment schedules and power availability. This phased approach allows us to efficiently convert advantaged infrastructure positions into incremental contracted capacity over time.
    Our strategy is designed to produce durable, infrastructure‑like cash flows while preserving flexibility to scale alongside accelerating demand for compute.
    Evolution of Our Business and Capital Allocation
    TeraWulf has undergone a deliberate strategic transition toward HPC hosting as its primary business. While the Company operates legacy bitcoin mining facilities and leverages this flexible compute load to support early HPC infrastructure development, going forward capital allocation will be focused on HPC data center development, long-term hosting arrangements, and infrastructure supporting AI-driven compute workloads.
    While the Company currently derives the majority of its revenue from bitcoin mining, HPC hosting is now the Company’s primary growth driver and operating focus.
    Power Strategy and Responsible Design
    TeraWulf’s power strategy emphasizes reliability, efficiency, and responsible integration with regional electric grids. Our campuses are designed to operate with long-duration, cost-competitive power resources that support both customer uptime requirements and broader grid stability.
    The Company’s development and operations team brings deep experience in power generation, transmission, interconnection, and large-scale energy infrastructure, which informs site selection, facility design, and day-to-day operations. This expertise enables TeraWulf to evaluate and develop complex, power-intensive sites efficiently and to structure infrastructure solutions that support high-density, mission-critical compute. We believe this power and infrastructure experience provides meaningful differentiation relative to many data center developers that do not have comparable in-house energy expertise.
    As part of this strategy, the Company expects to acquire and develop sites that may include on-site generation, battery storage, and other dispatchable resources, primarily to enhance reliability for mission-critical compute and to support grid operations where appropriate. These assets are intended to improve operational resilience, enable participation in ancillary services, and reduce congestion and volatility on regional power systems. Rather than relying on a singular energy narrative, TeraWulf focuses on responsible facility design, efficient power utilization, and long-term infrastructure stewardship.
    Environmental and Power Considerations
    TeraWulf’s approach to environmental and energy considerations is grounded in responsible infrastructure design, operational efficiency, and reliable integration with regional electric grids. The Company develops and operates digital infrastructure on existing industrial and energy sites, prioritizing reuse of legacy assets and minimizing incremental land disturbance.
    Our data center campuses are engineered to support high-density, mission-critical compute while emphasizing efficient power utilization, advanced cooling architectures, and resilient electrical design. These facilities are designed to operate with a range of long-duration power resources, including grid-supplied electricity and, where appropriate, on-site generation.
    The Company’s environmental focus is centered on disciplined development, efficient operations, and long-term infrastructure stewardship rather than reliance on any single energy source or environmental attribute.
    Our Facilities
    2

    Lake Mariner Data Campus
    The Lake Mariner Data Campus is TeraWulf’s flagship HPC campus and a core component of the Company’s contracted HPC platform. Located in Barker, New York on the site of a former coal‑fired power plant that was retired and repurposed into a modern digital infrastructure campus, operations commenced in March 2022. The site benefits from substantial existing transmission infrastructure and is designed for scalable expansion.
    As of December 31, 2025, the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 MW of critical IT HPC capacity. The campus is undergoing phased expansion to support additional HPC contracted deployments with gross capacity of approximately 500 MW in the near term, with potential expansion to approximately 750 MW, subject to additional approvals from the NYISO.
    The Lake Mariner Data Campus sources power from the NYISO Zone A grid, which is characterized by low-cost, low-carbon energy. Of the campus’s total power needs, 90 MW is allocated under an agreement with the New York Power Authority (“NYPA”) executed in February 2022, providing high-load factor power under a ten-year term commencing with NYPA’s initial power delivery.
    The Lake Mariner Data Campus is designed to support multiple hyperscale and enterprise tenants through modular, phased development and incorporates advanced liquid-cooling systems, redundant electrical architectures, and scalable mechanical and network infrastructure optimized for high-density GPU deployments.
    TeraWulf operates the Lake Mariner Data Campus through its subsidiaries La Lupa Data LLC (“La Lupa”) and Akela Data LLC (“Akela”). Collectively, La Lupa and Akela represent 438 MW of contracted critical IT HPC capacity at the Lake Mariner Data Campus, with some deliveries having commenced in 2025 and others extending into 2026.
    La Lupa
    In December 2024, La Lupa entered into long-term data center lease agreements with Core42 (the “Core42 Leases”), pursuant to which we committed to deliver 60 MW of critical IT load. The Core42 Leases have an initial ten-year term with two five-year renewal options and include customary provisions governing operating standards, service levels, and expansion rights. Construction commenced in 2024 and continued into 2025; commissioning activities commenced in 2025 with phased deliveries aligned to meet Core42’s deployment schedule.
    Akela
    In August 2025, Akela entered into three data center lease agreements (the “Akela Fluidstack Leases”) with Fluidstack USA I Inc. (together with its affiliates, “Fluidstack”), a leading AI cloud platform. Under the Akela Fluidstack Leases, we will provide 378 MW of critical IT load at the Lake Mariner Data Campus. The Akela facilities are being developed in multiple phases, with construction having commenced in 2025 and delivery expected to commence in 2026.
    The Akela Fluidstack Leases benefit from substantial credit support provided by Google, which supports Fluidstack’s payment and performance obligations under the leases and materially enhances the credit quality and bankability of our contracted lease revenues. This credit support was a key factor in enabling efficient financing and phased development of the Akela facilities.
    Abernathy HPC Campus
    The Abernathy HPC Campus reflects the extension of the Company’s relationship with Fluidstack, also supported by credit enhancement from Google, to an additional site in Texas. The campus is being developed through a joint venture in which the Company holds a 50.1% ownership interest.
    In October 2025, the Company entered into an amended and restated limited liability company agreement (the “Abernathy Joint Venture Agreement”) with Fluidstack CS I Inc. (the “Fluidstack Member”) to govern the terms of operation of FS CS 1 LLC (the “Abernathy Joint Venture”), which will develop, lease and operate the Abernathy HPC Campus.
    The Abernathy HPC Campus is designed for 168 MW critical IT load, representing the full build-out of the site. This capacity is fully pre-leased to Fluidstack USA III under a 25-year data center lease with built-in rent escalators and options for term contraction (the “Abernathy Fluidstack Lease” and, together with the Akela Fluidstack Leases, the
    3

    “Fluidstack Leases”). Construction is proceeding in phases, with completion and delivery currently targeted for the second half of 2026.
    Similar to Akela, the Abernathy Fluidstack Lease benefits from credit support from Google, which provides financial support for Fluidstack’s obligations under the sublease, materially strengthening the risk profile of our contracted revenues and facilitating third-party financing.
    Infrastructure First Growth Model
    Across all campuses, TeraWulf prioritizes reuse of existing industrial and energy infrastructure, accelerated permitting pathways, and disciplined expansion aligned with customer demand. By combining utility-scale infrastructure control, long-term contracted revenues supported by credit-enhanced counterparties, and a scalable development pipeline, the Company is positioned to support the growing demand for AI and high-density compute while delivering durable value to shareholders.
    Our Strengths
    Infrastructure Control and Vertical Integration
    TeraWulf’s business is built around long-term control of digital infrastructure assets, including land use through ownership or long-term ground leases, interconnection rights, data center buildings, electrical and cooling systems, and, where applicable, on-site generation. This infrastructure-centric model enables disciplined execution across development and operations, enhances reliability, and supports efficient delivery of large-scale HPC capacity.
    Direct control over critical infrastructure allows the Company to maintain governance authority, manage development risk, and align capital deployment with long-term customer commitments, while supporting transparency and accountability for stakeholders.
    Reliable and Cost-Competitive Power Strategy
    TeraWulf develops and operates its campuses in power-advantaged markets with access to long-duration, cost-competitive electricity. Our infrastructure is designed to support high-load-factor operations and mission-critical compute, while maintaining flexibility to integrate grid-supplied power and, where appropriate, on-site dispatchable resources.
    This approach supports predictable operating costs, enhances resilience, and enables participation in grid-support mechanisms, positioning the Company to serve hyperscale and enterprise customers with demanding uptime and performance requirements.
    Scalable Platform with Embedded Expansion Optionality
    TeraWulf’s campuses are designed for modular, phased expansion, allowing capacity to be added efficiently as customer demand materializes. The Company’s development pipeline leverages existing industrial sites, established interconnection, and scalable electrical and cooling architectures to shorten development timelines and reduce execution risk.
    At the Lake Mariner Data Campus, the Company can scale capacity to approximately 500 MW in the near term and up to approximately 750 MW with additional approvals from the NYISO. Together with the Abernathy HPC Campus and the Cayuga Site, this platform supports the Company’s objective of contracting 250 MW to 500 MW of new critical IT HPC capacity annually, subject to market conditions and power availability.
    Experienced Management and Operations Team
    TeraWulf’s senior management team brings decades of experience in energy infrastructure development, ownership, and operations, including large-scale power generation and industrial asset redevelopment. This experience underpins the Company’s ability to execute complex projects, manage grid interdependencies, and operate mission-critical infrastructure. To align management incentives with long-term shareholder value, a substantial portion of our senior management and director compensation is equity-based.
    The Company also benefits from the expertise of its subsidiary Beowulf Electricity & Data LLC (“Beowulf E&D”), which supports development, construction, and operational functions. The Beowulf E&D team has more than 30
    4

    Loading financial statements...

    Financial statements

    data from SEC XBRL filings. Values are as-reported; restatements supersede originals. Values reported in .

    From 10-Q filed 2026-11-06 (period ending 2026-09-30).


    ITEM 2.    Management’s Discussion and Analysis of Financial Condition and Results of Operations
    The following Management’s Discussion and Analysis of Financial Condition and Results of Operations should be read in conjunction with a review of the other Items included in this Quarterly Report on Form 10-Q, as well as our audited consolidated financial statements and related notes as disclosed in our Annual Report on Form 10-K for the fiscal year ended December 31, 2025. All figures presented below represent results from continuing operations, unless otherwise specified. Capitalized terms used but not otherwise defined herein shall have the meanings ascribed to such terms in the consolidated financial statements. Unless the context otherwise requires, references in this Quarterly Report on Form 10-Q to the “Company,” “TeraWulf,” “we,” “us” or “our” refer to TeraWulf Inc. and its consolidated subsidiaries, unless otherwise indicated. Some of the information contained in this discussion and analysis, including information with respect to our plans and strategies for our business, includes forward-looking statements that involve risks and uncertainties. You should review the sections titled “Forward-Looking Statements” and “Risk Factors” for a discussion of forward-looking statements and important factors that could cause our actual results to differ materially from the results described in or implied by the forward-looking statements contained in the following discussion and analysis.
    Overview
    We are a vertically integrated owner, developer, and operator of digital infrastructure assets in the United States, purpose-built to support HPC workloads, including AI, machine learning, and advanced cloud applications.
    During the three and nine months ended September 30, 2026, HPC leasing revenue represented a majority of total revenue, reflecting the continued ramp of long-term contracted capacity at the Lake Mariner Data Campus.
    The Company has undergone a deliberate strategic transition toward HPC leasing as its primary growth driver and operating focus. While TeraWulf historically operated bitcoin mining facilities and used flexible compute loads to support the development of its infrastructure platform, the Company has begun to curtail and repurpose portions of that infrastructure to support HPC development. Going forward, the Company’s capital allocation, development activities and operating focus are centered on HPC data center development, long-term data center leases and infrastructure supporting AI-driven compute workloads. The Company intends to continue bitcoin mining operations where they remain economically attractive and do not conflict with HPC development.
    Our strategy is grounded in controlling utility-scale infrastructure and pairing compute-optimized facilities with reliable, long-duration power resources. Through ownership or long-term control of land, interconnection rights and electrical and cooling infrastructure - and, where appropriate, on-site generation - the Company seeks to deliver resilient, cost-efficient capacity to hyperscale and enterprise customers under long-term data center leases. These arrangements generally range from 10 to 25 years and, in certain cases, benefit from investment-grade credit support, enhancing the durability and bankability of contracted revenues. The Company expects these arrangements to provide long-term revenue visibility and support project-level financing as the platform scales.
    The Company’s platform is differentiated by its control of utility-scale infrastructure, deep in-house power and grid expertise, and a scalable development model supported by long-term, credit-enhanced customer contracts.
    Strategy Execution and Capital Allocation
    Management’s execution of the Company’s strategy is focused on converting advantaged infrastructure positions into long-term, contracted HPC capacity. This includes the phased conversion of existing infrastructure, where appropriate, and the development of new campuses aligned with customer deployment schedules and power availability. This execution model emphasizes vertical integration, long-duration customer contracts supported by credit enhancement and disciplined, phased development.
    A core element of this approach is infrastructure control. By retaining control over land use, interconnection rights and electrical and cooling systems—and on-site generation where appropriate—the Company is able to manage development risk, optimize capital deployment and maintain operational oversight throughout the lifecycle of its facilities. Management believes this approach reduces execution risk relative to development models that rely more extensively on third parties.
    56

    The Company’s contracting strategy prioritizes long-term data center leases with credit-supported customers. These arrangements reduce the Company’s exposure to commodity-driven revenue streams, including bitcoin price volatility, as its revenue mix continues to shift toward contracted HPC leasing. They also provide long-term revenue visibility, support project-level financing and reduce cash-flow volatility as the platform scales. Credit enhancement associated with certain customer contracts has been an important factor in accelerating development timelines and facilitating third-party financing.
    Each campus is designed for modular, multi-phase expansion. Initial phases are intended to deliver near-term contracted capacity, while subsequent phases are aligned with customer deployment schedules and infrastructure readiness, including power availability and interconnection timing. Management believes this phased approach allows the Company to scale efficiently while maintaining capital discipline.
    While the Company currently derives a significant portion of its revenue from bitcoin mining, HPC leasing is now the Company’s primary growth driver and operating focus.
    Strategic Transactions
    Acquisition of Beowulf E&D
    On May 21, 2025 (the “Beowulf Acquisition Date”), the Company acquired 100% of the membership interests in Beowulf Electricity & Data LLC, Beowulf E&D (NY) LLC and Beowulf E&D (MD) LLC (collectively, “Beowulf E&D”). Additional detail regarding the consideration paid and contingent consideration associated with the Beowulf E&D acquisition is included in Note 3 to the condensed consolidated financial statements in Item 1 of this Quarterly Report on Form 10-Q.
    The acquisition materially expanded the Company’s internal capabilities across power infrastructure development, site operations, engineering, and project execution. Approximately 94 employees transitioned to the Company as part of the transaction. Management believes this acquisition strengthened operational integration and execution capability as the Company scales its HPC platform.
    Cayuga Site Ground Lease
    On August 12, 2025, the Company entered into a long-term ground lease for approximately 183 acres in Lansing, New York. Upon completion of permitting and site development, the Cayuga Site has the potential for up to 400 MW of gross capacity, supporting approximately 320 MW of critical IT load. The Cayuga Site provides an additional anchor location with existing interconnection and supporting infrastructure and represents a key component of the Company’s forward development pipeline.
    Abernathy Joint Venture
    On October 27, 2025, the Company entered into an amended and restated limited liability company agreement governing the Abernathy Joint Venture. The Company held a 50.1% equity interest in the joint venture. The Abernathy HPC Campus is designed for 168 MW of critical IT load, representing the full build-out of the site. The campus is 100% pre-leased to Fluidstack under a 25-year data center sublease with contractual rent escalators and options for term contraction. Lease obligations are supported by investment-grade credit enhancement provided by Google, materially strengthening the credit profile of the contracted revenues and facilitating third-party debt financing.
    In July 2026, the Company entered into a definitive agreement selling its entire 50.1% equity interest in the Abernathy Joint Venture to a group of purchasers for an aggregate cash consideration of approximately $530.0 million, representing a premium to the Company’s invested capital. The consideration is payable in installments in 2026 and 2027. The Company believes this sales transaction realizes the value created through the Company’s initial investment and provides capital for redeployment into wholly owned AI infrastructure, where the Company retains direct ownership, customer relationships, and operational control.
    57

    Justified Data Campus
    In February 2026, the Company entered into an Agreement of Purchase and Sale for a former industrial site (the “Justified Data Site”) in Hawesville, Kentucky (the “Justified Data Campus”). The Justified Data Campus is a strategically located brownfield infrastructure site which includes more than 250 buildable acres with immediate access to power infrastructure, including multiple high-voltage transmission lines, an on-site energized substation, and a direct connection to the regional transmission network. The Company is developing an AI/HPC data center campus at the Justified Data Site. In July 2026, the Company entered into long-term data center lease agreements with Anthropic for approximately 401 MW of critical IT capacity. Initial capacity is expected to be delivered in late 2027, with phased deliveries continuing through the second quarter of 2028. In August 2026, the Kentucky Public Service Commission approved a Retail Electric Service Agreement providing for up to 482 MW of electric service to the campus through Kenergy Corp. and Big Rivers Electric Corporation. The Justified Data Campus further diversifies the Company’s geographic footprint and supports growing customer demand for large-scale HPC infrastructure.
    Muskie Data Campus
    In May 2026, the Company acquired 100% of the membership interests of Industrial Equity Partners LLC, which owned or held contractual rights to purchase approximately 308 acres of land in Grayson, Kentucky (the “Muskie Data Campus”). The Muskie Data Campus is a hyperscale AI/HPC development site.
    In May 2026, the Company also entered into electric service and transmission infrastructure agreements with Kentucky Power Company, an American Electric Power company, providing for 500 MW of contracted electric service at the Muskie Data Campus. In October 2026 and November 2026, the Company executed amended and restated agreements increasing contracted capacity to 1,000 MW, subject to approval by the Kentucky Public Service Commission. The initial 500 MW is expected to begin ramping in the fourth quarter of 2028, with the additional 500 MW targeted for delivery in 2029. The amended agreements also provide for additional financial commitments and collateral requirements, as further described in Note 3 to the condensed consolidated financial statements in Item 1 of this Quarterly Report on Form 10-Q.
    Kentucky Power Company has committed to construct a 345 kV substation connected to the existing 765 kV transmission network, providing redundant, utility-scale power infrastructure designed to support the full 1,000 MW Muskie Data Campus. Together with the Company’s Justified Data Campus, which has up to 482 MW of approved electric service capacity, the Muskie Data Campus represents the Company’s second major digital infrastructure campus in Kentucky. This further expands the Company’s presence in a state that continues to emerge as an attractive market for large-scale AI/HPC development due to its robust energy infrastructure, supportive business environment, and strong engagement from state and local stakeholders.
    Operations Overview
    Lake Mariner Data Campus
    The Lake Mariner Data Campus is TeraWulf’s flagship HPC campus and a core component of the Company’s contracted HPC platform. The Lake Mariner Data Campus is located in Barker, New York on the site of a former coal-fired power plant that was retired and repurposed into a modern digital infrastructure campus with operations that commenced in March 2022. The site benefits from substantial existing transmission infrastructure and is designed for scalable expansion.
    As of September 30, 2026, the Lake Mariner Data Campus had 102 MW of energized critical IT HPC capacity and 145 MW of legacy bitcoin mining capacity. The campus is undergoing phased expansion to support additional contracted HPC deployments, with approximately 500 MW of aggregate gross capacity expected to be energized by early 2027, and planned expansion to approximately 750 MW, supported by an approved NYISO System Impact Study. During the nine months ended September 30, 2026, certain mining facilities were curtailed or repurposed to support HPC development, consistent with the Company’s strategic transition.
    The Lake Mariner Data Campus sources power from the NYISO Zone A grid, which is characterized by low-cost, low-carbon energy. Of the campus’s total power needs, 90 MW is allocated under an agreement with the New York Power Authority (“NYPA”) executed in February 2022, providing high-load factor power under a ten-year term commencing with NYPA’s initial power delivery.
    The Lake Mariner Data Campus is designed to support multiple hyperscale and enterprise tenants through modular, phased development and incorporates advanced liquid-cooling systems, redundant electrical architectures, and scalable mechanical and network infrastructure optimized for high-density GPU deployments.
    58

    TeraWulf operates the Lake Mariner Data Campus through its subsidiaries La Lupa Data LLC (“La Lupa”) and Akela Data LLC (“Akela”). Collectively, La Lupa and Akela represent 438 MW of contracted critical IT HPC capacity at the Lake Mariner Data Campus, with some deliveries having commenced in 2025 and during the nine months ended September 30, 2026, and others extending into the fourth quarter of 2026 and early 2027.
    La Lupa
    In December 2024, La Lupa entered into long-term data center lease agreements with Core42 (the “Core42 Leases”), pursuant to which we committed to deliver 60 MW of critical IT load. The Core42 Leases have an initial ten-year term with two five-year renewal options and include customary provisions governing operating standards, service levels, and expansion rights. Construction commenced in 2024 and continued into 2025 and 2026; commissioning activities commenced in 2025 with phased deliveries aligned to meet Core42’s deployment schedule. As of September 30, 2026, the Core42 data centers had been fully delivered and the full 60 MW of contracted critical IT capacity under the Core42 Leases was in service.
    Akela
    In August 2025, Akela entered into three data center lease agreements (the “Akela Fluidstack Leases”) with Fluidstack USA I Inc. (together with its affiliates, “Fluidstack”), a leading AI cloud platform. Under the Akela Fluidstack Leases, as amended, we agreed to provide 378 MW of critical IT load at the Lake Mariner Data Campus, which represents the majority of the remaining contracted HPC capacity at the Lake Mariner Data Campus. As of September 30, 2026, one Akela Fluidstack Lease had commenced operations, with the remaining contracted capacity scheduled for phased commencement during the fourth quarter of 2026 and the first half of 2027.
    The Akela Fluidstack Leases benefit from substantial credit support provided by Google, which supports Fluidstack’s payment and performance obligations under the leases and materially enhances the credit quality and bankability of our contracted lease revenues. This credit support was a key factor in enabling efficient financing and phased development of the Akela facilities.
    Abernathy HPC Campus
    In October 2025, the Company entered into an amended and restated limited liability company agreement (the “Abernathy Joint Venture Agreement”) with Fluidstack CS I Inc. (the “Fluidstack Member”) to govern the terms of operation of FS CS 1 LLC (the “Abernathy Joint Venture”), which was established to develop, lease and operate the Abernathy HPC Campus.
    In July 2026, the Company entered into a Membership Interest Purchase Agreement (the “Purchase Agreement”) with the Fluidstack Member and certain other purchasers (collectively, the “Purchasers”) pursuant to which the Company sold to the Purchasers all of the Company’s 50.1% membership interest in the Abernathy Joint Venture for aggregate cash consideration of approximately $530.0 million. As a result of this transaction, the Company no longer holds an equity interest in the Abernathy Joint Venture.
    Regional Diversification and Platform Resilience
    The development of the Justified Data Campus and the Muskie Data Campus provides the Company with meaningful regional diversification. By expanding its HPC platform beyond New York into the regions operated by the Mid-continent Independent System Operator (“MISO”) and PJM Interconnection, L.L.C. (“PJM”), the Company reduces its concentration in any single power market, regulatory framework or geographic area.
    Geographic diversification reduces the Company’s concentration in any single power market or regulatory jurisdiction and may mitigate the impact of localized weather events and operational disruptions. Management believes this diversification enhances overall platform resilience, supports customer deployment flexibility and strengthens the Company’s ability to maintain continuity of operations across its portfolio.
    Power Strategy
    The Company’s power strategy emphasizes reliability, efficiency, and responsible integration with regional electric grids. The Company’s campuses are designed to operate with long-duration, cost-competitive power resources that support both customer uptime requirements and broader grid stability.
    59

    The Company’s development and operations team brings deep experience in power generation, transmission, interconnection, and large-scale energy infrastructure, which informs site selection, facility design, and day-to-day operations. This expertise enables the Company to evaluate and develop complex, power-intensive sites efficiently and to structure infrastructure solutions that support high-density, mission-critical compute. The Company believes this power and infrastructure experience provides meaningful differentiation relative to many data center developers that do not have comparable in-house energy expertise.
    As part of this strategy, the Company expects to acquire and develop sites that may include on-site generation, battery storage, and other dispatchable resources, primarily to enhance reliability for mission-critical compute and to support grid operations where appropriate. These assets are intended to improve operational resilience, enable participation in ancillary services, where applicable, and support reliable, long-duration power supply for compute workloads. Rather than relying on a singular energy narrative, the Company focuses on responsible facility design, efficient power utilization, and long-term infrastructure stewardship.
    Liquidity and Capital Resources
    The Company’s primary sources of liquidity include cash on hand, cash generated from operations, sale proceeds from bitcoin, equity issuances, debt financing, and project-level financing arrangements. As of September 30, 2026, the Company had approximately $2.4 billion of cash, cash equivalents, and restricted cash. Capital requirements are driven primarily by HPC data center development, including significant capital expenditures associated with site development, electrical and mechanical infrastructure, and customer-specific fit-out.
    Management expects future capital deployment to prioritize contracted HPC projects and disciplined expansion of the Company’s development pipeline. The Company continues to evaluate debt, equity and project-level financing alternatives based on project requirements, customer commitments and prevailing market conditions, while seeking to manage balance-sheet risk.
    Outlook
    The Company expects future results to be increasingly influenced by the development and operation of its HPC data center platform. As contracted HPC capacity is delivered and energized and legacy bitcoin mining infrastructure is further curtailed or repurposed, the Company expects its revenue mix to continue shifting toward HPC leasing.
    Future performance will depend on the timing of construction, commissioning, customer deployment schedules, access to power and interconnection, and the availability of project-level financing. Management expects capital deployment in future periods to be focused primarily on contracted HPC projects and disciplined expansion of the Company’s development pipeline.
    The table below presents the lease and nonlease components of HPC lease revenue for the three and nine months ended September 30, 2026 and 2025 (in thousands):
    Three Months Ended September 30,Nine Months Ended September 30,
    2026202520262025
    HPC lease revenue(1)
    Rent
    $46,034 $5,748 $90,519 $5,748 
    Power passthrough(2)
    5,383 326 8,374 326 
    Tenant fit-out11,277 879 16,173 879 
    Maintenance and other
    292 250 874 250 
    Total HPC lease revenue
    $62,986 $7,203 $115,940 $7,203 
    Cost of revenue (exclusive of depreciation)(2)
    $15,398 $326 $22,301 $326 
    (1)    As of September 30, 2026, all Core42 Leases and one Akela Fluidstack Lease had commenced, representing an aggregate of 102 MW of operational, revenue-generating critical IT capacity.
    (2)    Cost of revenue (exclusive of depreciation) represents power costs which are passed through to the customer without markup and are included on a gross basis in HPC lease revenue as well as includes costs incurred by the Company in connection with its fit-out services under the HPC Leases.
    60

    Bitcoin Mining Operations
    As of September 30, 2026, we owned approximately 48,700 miners, with approximately 33,300 operational at our bitcoin mining facilities on the Lake Mariner Data Campus (the “LMD Bitcoin Mining Facilities”) and the remainder undergoing maintenance, awaiting disposal or on standby to replace miners under repair. These miners were comprised as follows:
    Vendor and ModelNumber of miners
    Bitmain S19 XP4,300 
    Bitmain S19j XP8,000 
    Bitmain S19k Pro1,500 
    Bitmain S218,200 
    Bitmain S21 Pro26,700 
    48,700 
    As of September 30, 2026, our fleet of miners ranged in age from 1.4 years to 3.5 years with an average age of approximately 2.1 years. We do not have scheduled downtime for our miners and while we periodically perform unscheduled maintenance on our miners. When performing unscheduled maintenance, depending on the length of estimated repair time, we may replace a miner with a substitute miner to limit overall downtime. As of September 30, 2026, our fleet of miners at the LMD Bitcoin Mining Facilities had a range of energy efficiency from 15.0 to 23.0 joules per terahash (“j/th”) and has an average energy efficiency of 16.2 j/th.
    Bitcoin Mining - Share of Global Hashrate
    Several factors influence our ability to mine bitcoin profitably, including bitcoin’s USD value, mining difficulty, global hashrate, power costs, fleet energy efficiency, and overall data center efficiency. Among these, energy efficiency is a critical driver of profitability, as power costs represent the most significant direct expense in bitcoin mining. We believe we operate a highly efficient mining fleet, optimized to maximize output while minimizing energy consumption. To assess operational performance and effectiveness, the Company tracks key metrics, which we believe are also valuable to investors for evaluating our progress and benchmarking against industry peers.
    The table below presents our miner efficiency and computing power as compared to the global computing power as of September 30, 2026 and 2025:
    Combined facilitiesSeptember 30, 2026September 30, 2025
    Global hashrate (EH/s)(1)
    931.0 1,139.0 
    Miner efficiency (j/th)(2)
    16.4 17.5 
    TeraWulf operational hashrate (EH/s)(3)
    5.7 8.5 
    TeraWulf percentage of global hashrate0.6 %0.7 %
    (1)    Total global hashrate obtained from YCHARTS (https://ycharts.com/indicators/bitcoin_network_hash_rate).
    (2)    Joules of energy required to produce each terahash of processing power
    (3)    While nameplate at the LMD Bitcoin Mining Facilities was 9.8 EH/s and 11.6 EH/s as of September 30, 2026 and 2025, respectively, actual operational hashrate depends on a variety of factors, including (but not limited to) performance tuning to increase efficiency and maximize margin, scheduled outages (scopes to improve reliability or performance), unscheduled outages, curtailment due to participation in various cash generating demand response programs, derate of ASICS due to adverse weather and ASIC maintenance and repair.

    As of September 30, 2026, our operational hashrate represented approximately 0.6% of the total global hashrate, aligning with our share of global blockchain rewards. As of that date, this translated to approximately 2 bitcoin mined per day. To maintain profitability, we focus on operational efficiency and cost management, with the objective of generating mining revenue sufficient to cover direct operating expenses.
    61

    Bitcoin Mining - Average Cost of Bitcoin Mined
    The table below presents the average cost of mining each bitcoin, including bitcoin mined at the LMD Bitcoin Mining Facilities for the three and nine months ended September 30, 2026 and 2025 and the total energy cost per kWh utilized within the facilities.
    Three Months Ended September 30,Nine Months Ended September 30,
    Cost of mining - Analysis of costs to mine one bitcoin2026202520262025
    Cost of mining - Lake Mariner Data Campus
    Cost of energy per bitcoin mined$52,634 $44,655 $33,049 $51,457 
    Other direct costs of mining - non energy utilities per bitcoin mined$140 $74 $146 $66 
    Cost to mine one bitcoin(1)
    $52,774 $44,729 $33,195 $51,523 
    Value of each bitcoin mined(2)
    $71,204 $115,053 $73,163 $101,658 
    Cost to mine one bitcoin as % of value of bitcoin mined74.1 %38.9 %45.4 %50.7 %
    Statistics
    Lake Mariner Data Campus
    Total bitcoin mined
    186 377 534 1,234 
    Total value of bitcoin mined(2) ($ in thousands)
    $13,244 $43,375 $39,069 $125,416 
    Total MWhs utilized162,558 357,754 488,527 1,080,404 
    Total energy expense, net of expected demand response proceeds ($ in thousands)
    $9,790 $16,835 $17,648 $63,482 
    Cost per kWh$0.060 $0.047 $0.036 $0.059 
    Energy expense, net as % of value of bitcoin mined73.9 %38.8 %45.2 %50.6 %
    Other direct costs of mining ($ in thousands)
    $26 $28 $78 $82 

    (1)    “Cost to mine one bitcoin” is a cash cost metric and does not include depreciation. Although the Company recognizes depreciation with respect to its mining assets, it does not consider depreciation in determining whether it is economical to operate its mining equipment. As a result, the Company does not consider the sunk costs or depreciation of past capital investments in its historical or forecasted breakeven analysis. If depreciation of our miner fleet were factored into the above cost of mining analysis, it would add $50,790 and $60,558 for the three and nine months ended September 30, 2026, respectively, bringing the total cost to mine one bitcoin to $103,564 and $93,753 for the three and nine months ended September 30, 2026, respectively. If depreciation of our miner fleet were factored into the above cost of mining analysis, it would add $70,277 and $49,335 for the three and nine months ended September 30, 2025, bringing the total cost to mine one bitcoin to $115,006 and $100,858 for the three and nine months ended September 30, 2025, respectively.
    (2)    Computed as the weighted-average opening price of bitcoin on each respective day the mined bitcoin is earned.

    Power costs are the most significant expense in our bitcoin mining operations. During the three and nine months ended September 30, 2026, the Company incurred gross power costs of $13.0 million and $37.7 million, respectively. In addition, during the three and nine months ended September 30, 2026 and 2025, the Company curtailed operations at the LMD Bitcoin Mining Facilities in response to weather events, energy price spikes, and participation in demand response programs. The Company records expected payments to be received for demand response programs as a reduction in cost of revenue, which amounted to $3.2 million and $20.1 million for the three and nine months ended September 30, 2026, respectively, and $7.4 million and $13.3 million for the three and nine months ended September 30, 2025. During the nine months ended September 30, 2026, there were significant curtailment periods for the Company’s bitcoin mining operations due to sustained low temperatures throughout the Northeastern United States which led to significantly reduced power consumption and significantly higher demand response proceeds for the Lake Mariner Data facility resulting in a lower than typical cost of power for the period.
    Energy prices are highly volatile, influenced by global events that can drive nationwide fluctuations in power costs. At the LMD Bitcoin Mining Facilities, power costs are subject to variable market rates, which can change hourly based on wholesale electricity pricing. While this introduces some unpredictability, it also provides us with the flexibility to actively manage our energy consumption, optimizing for profitability and efficiency. Energy prices are also highly sensitive to weather conditions, such as winter storms and polar vortices, which can increase regional power demand and drive up costs. During such events, we may curtail operations to avoid consuming power at peak rates, or we may be
    62

    curtailed under demand response programs in which we participate. The average aggregate realized power prices at the LMD Bitcoin Mining Facilities were $0.060 and $0.036 per kilowatt hour during the three and nine months ended September 30, 2026, respectively, and $0.047 and $0.059 the three and nine months ended September 30, 2025.
    Our management team continuously monitors market conditions to determine when and for how long to curtail operations. If curtailment is not mandated under demand response programs, we make real-time decisions to curtail mining whenever power prices exceed the value of the fixed bitcoin reward. As a result, curtailment increases when bitcoin’s value declines or energy prices rise, and decreases when bitcoin’s value appreciates or energy costs fall. These decisions are actively managed on an hour-by-hour basis to optimize profitability.
    The Company has purchased all miners with cash, without relying on limited recourse equipment financing for miner acquisitions. To support operations and purchase miners and other fixed assets, we have raised capital through both equity issuances and corporate-level debt. Costs related to these capital raises are not included in this analysis.
    Miner acquisition costs, or capital expenditures, are not factored into the cost of mining analysis, as they do not impact the marginal cost of producing one bitcoin. Instead, these costs are recorded as property, plant, and equipment in the condensed consolidated balance sheets. Depreciation of property, plant, and equipment is calculated using the straight-line method, with estimated useful lives of four years for miners and five years for computer equipment.
    During the three and nine months ended September 30, 2026, the Company recorded accelerated depreciation expense of $7.7 million and $22.2 million, respectively, related to a certain miner building and related miners of which the Company shortened their useful lives based on expected shutdown of operations for purposes of supporting the HPC operations. During the three and nine months ended September 30, 2025, the Company recorded accelerated depreciation expense of $7.8 million related to the planned decommissioning of one miner building in early 2026 including all miners and infrastructure. However, if depreciation were included in the cost of mining analysis, it would add $50,790 and $60,558 for the three and nine months ended September 30, 2026, respectively, and $70,277 and $49,335 for the three and nine months ended September 30, 2025, respectively.
    Estimating asset useful lives requires management judgment, particularly given the rapid evolution of next-generation mining rigs in industrial-scale bitcoin mining. Depreciation schedules may be adjusted if events, regulatory changes, or shifts in operating conditions indicate a need for revision. Management continuously evaluates factors such as future energy market conditions, operating costs, maintenance practices, and capital investment needs to ensure depreciation assumptions remain reasonable. When an asset’s estimated useful life is adjusted—either shortened or extended—depreciation provisions are updated accordingly, which could have a material impact on future financial results.
    Recent Developments
    Muskie Data Campus Power Agreements
    On October 1, 2026, the Company entered into amended and restated electric service and transmission infrastructure agreements with Kentucky Power Company relating to the Muskie Data Campus. The amended electric service agreement increases contracted power capacity from 500 MW to 1,000 MW, with the additional capacity expected to become available in phases through October 2029, subject to approval by the Kentucky Public Service Commission. The amended agreements also provide for additional collateral, customer bill credits and other financial commitments. For further information reference Notes 3 and 12 to the condensed consolidated financial statements in Item 1 of this Quarterly Report on Form 10-Q.
    Revolving Credit Facility Amendment
    On October 23, 2026, the Company entered into an amendment to its Revolving Credit Agreement, increasing aggregate commitments under the Revolving Credit Facility from $250.0 million to $400.0 million. The amendment also provides for an uncommitted accordion feature of up to $150.0 million, eliminates the existing $150.0 million letter-of-credit sublimit and increases the aggregate limit on borrowings and letters of credit outstanding prior to the First Commencement Date from $75.0 million to $150.0 million. The amendment further provides for the release of certain collateral upon satisfaction of specified conditions. For further information reference Note 10 to the condensed consolidated financial statements in Item 1 of this Quarterly Report on Form 10-Q.
    63

    Google Credit Backstop and Fluor EPC Agreement
    On November 4, 2026, the Company, certain of its subsidiaries and Anthropic entered into credit support agreements with Google in connection with each of the Anthropic HPC Leases.
    Pursuant to the credit support agreements, Google will backstop certain obligations of Anthropic under the Anthropic HPC Leases, effective upon commencement of the last data hall under the corresponding Anthropic HPC Lease. Specifically, in the event of a payment default under an Anthropic HPC Lease, or if Anthropic becomes subject to an insolvency event, following notice from the landlord subsidiary, Google will have the option to (i) pay all rent currently due under the applicable lease and assume the lease as the tenant or (ii) under certain circumstances, permit termination of the lease and pay a termination fee pursuant to the applicable credit support agreement. In addition, in the event of a payment default (without an insolvency event), Google may defer its election of the foregoing options (i) and (ii) for a certain specified period, during which deferral period Google will pay all unpaid rent and any additional rent that becomes due and remains unpaid by Anthropic. Within the first six years following the effectiveness of the applicable credit support backstop, Google may elect for the lease to be terminated only under limited circumstances relating to the installed equipment capacity in the relevant building.
    The termination fee required to be paid by Google under the credit support agreements, to the extent applicable, decreases over time and is subject to limits, including based on the amount of the related project financing. Upon payment of a termination fee, Google may elect to acquire an equity interest in the Company’s subsidiary that is the landlord under the applicable Anthropic HPC Leases.
    The backstop under the credit support agreements described above terminates under specified conditions, including when Anthropic, or a qualifying affiliate that guarantees its lease obligations, maintains the required investment-grade credit ratings for at least three months.
    In connection with the credit support agreements, the Company’s subsidiary that is the landlord under the Anthropic HPC Leases and Anthropic also agreed to amend the Anthropic HPC Leases.
    In October 2026, the Company entered into an engineering, procurement and construction agreement with Fluor Enterprises, Inc. for three data center buildings at the Justified Data Campus. The agreement covers engineering, procurement, construction, testing and commissioning, with guaranteed maximum pricing to be established as engineering and procurement progress. Phased ready-for-service completions are expected to begin in late 2027 and continue through the second quarter of 2028.
    Results of Operations
    The Company generates revenue in the form of bitcoin by providing hash computation services to a mining pool operator to mine bitcoin and validate transactions on the global bitcoin network using miners owned by the Company. The earned bitcoin are routinely sold for U.S. dollars.
    In July 2025, the Company commenced its HPC leasing operations. HPC lease revenue is generated by leasing data center space and providing related services to our HPC customers. These leasing agreements include lease components related to the right to use data center space and nonlease components for power delivery, physical security, and maintenance services. HPC power costs are passed through to the customer without markup and are included on a gross basis in HPC lease revenue. Additionally, the lease agreements provide for variable payments for certain fit-out services as requested by the customer which are passed through with a markup and are included on a gross basis in HPC lease revenue.
    The Company’s strategy is focused on developing and operating large-scale digital infrastructure for long-term HPC leasing, while continuing to manage its bitcoin mining operations for profitability. During the third quarter of 2026, HPC leasing represented approximately 83% of total revenue, compared to 14% in the prior-year period, reflecting the continued expansion of the Company’s contracted HPC business. We are confident our expertise in power infrastructure and digital asset mining can be favorably applied to the design, development, and operation of large-scale data centers. These data centers are optimized for high-value applications such as cloud computing, machine learning, and artificial intelligence. We are actively seeking opportunities to expand into these areas using our knowledge, expertise, and existing infrastructure wherever favorable market opportunities arise.
    64

    Revenue
    The following table presents revenue (in thousands):
    Three Months Ended September 30,Nine Months Ended September 30,
    2026202520262025
    Revenue:
    Digital asset revenue$13,244$43,375$39,069$125,416
    HPC lease revenue62,9867,203115,9407,203
    Total revenue$76,230$50,578$155,009$132,619
    Percentage of total revenue
    Digital asset revenue17%86%25%95%
    HPC lease revenue
    83%14%75%5%
    Total revenue100%100%100%100%
    Total revenue for the three months ended September 30, 2026 and 2025 was $76.2 million and $50.6 million, respectively, representing an increase of $25.6 million. Total revenue for the nine months ended September 30, 2026 and 2025 was $155.0 million and $132.6 million, respectively, representing an increase of $22.4 million. These changes were a result of the factors described below.
    Digital asset revenue for the three months ended September 30, 2026 and 2025 was $13.2 million and $43.4 million, respectively, a decrease of $30.2 million. Digital asset revenue for the nine months ended September 30, 2026 and 2025 was $39.1 million and $125.4 million, respectively, a decrease of $86.3 million. During the nine months ended September 30, 2026, two miner buildings were repurposed or placed out of service to support the HPC development at the Lake Mariner Data Campus and the Company significantly curtailed its bitcoin operations resulting in total bitcoin mined of 186 bitcoin during the three months ended September 30, 2026 as compared to 377 bitcoin mined during the same period in the prior year, and 534 bitcoin mined during the nine months ended September 30, 2026 as compared to 1,234 bitcoin mined during the same period in the prior year.
    Bitcoin prices averaged $71,204 and $73,163 per bitcoin during the three and nine months ended September 30, 2026, respectively, as compared to $114,390 and $102,192 per bitcoin during the three and nine months ended September 30, 2025, respectively.
    HPC lease revenue for the three and nine months ended September 30, 2026 was $63.0 million and $115.9 million, reflecting the continued ramp of long-term contracted capacity at the Lake Mariner Data Campus from 18 MW of HPC leasing capacity as of December 31, 2025 to 102 MW of HPC leasing capacity as of September 30, 2026.
    HPC lease revenue for the three and nine months ended September 30, 2025 was $7.2 million. In July 2025, TeraWulf commenced its HPC leasing operations and energized 18 MW of HPC leasing capacity at the Lake Mariner Data Campus.
    Costs and Expenses
    The following table presents cost of revenue (exclusive of depreciation) (in thousands):
    Three Months Ended September 30,Nine Months Ended September 30,
    2026202520262025
    Cost of revenue (exclusive of depreciation)$25,188$17,123$39,949$63,770
    65

    Cost of revenue (excluding depreciation) for the three months ended September 30, 2026 and 2025 was $25.2 million and $17.1 million, respectively, representing an increase of $8.1 million. The increase is primarily due to an increase of $10.1 million of costs incurred by the Company in connection with its fit-out services under the HPC Leases and increase in gross power costs of $5.0 million related to HPC leasing activities during the three months ended September 30, 2026. The increase was partially offset by a decrease in gross power costs related to bitcoin mining operations of $11.2 million due to reduced bitcoin mining power consumption as the Company curtailed its mining operations and repurposed two miner buildings to support the expansion of HPC operations at the Lake Mariner Data Campus. Additionally, demand response proceeds decreased $4.2 million during the three months ended September 30, 2026 as compared to the same period in prior year.
    Cost of revenue (excluding depreciation) for the nine months ended September 30, 2026 and 2025 was $39.9 million and $63.8 million, respectively, representing a decrease of $23.8 million. The decrease was primarily driven by a decrease in gross power costs related to bitcoin mining operations of $39.0 million due to reduced bitcoin mining power consumption as the Company curtailed its mining operations and repurposed two miner buildings to support the expansion of HPC operations at the Lake Mariner Data Campus. The decrease was partially offset by an increase of $13.9 million of costs incurred by the Company in connection with its fit-out services under the HPC Leases and increase in gross power costs of $8.1 million related to HPC leasing activities during the nine months ended September 30, 2026. Additionally, demand response proceeds increased $6.8 million during the nine months ended September 30, 2026 as compared to the same period in prior year. The Company remains actively enrolled in such programs.
    The following table presents operating expenses (in thousands):
    Three Months Ended September 30,Nine Months Ended September 30,
    2026202520262025
    Operating expenses$37,742$2,921$68,463$6,104
    Operating expenses – related party1,7131,5825,6324,805
    $39,455$4,503$74,095$10,909
    Operating expenses (including related party) for the three months ended September 30, 2026 and 2025, were $39.5 million and $4.5 million, respectively, an increase of $35.0 million. Operating expenses increased primarily driven by the costs related to expansion of HPC operations and constructions activities at the our HPC sites of $35.3 million partially offset by a $0.3 million decrease in operating expenses related to bitcoin mining operations.
    Operating expenses (including related party) for the nine months ended September 30, 2026 and 2025, were $74.1 million and $10.9 million, respectively, an increase of $63.2 million. Operating expenses increased primarily driven by the costs related to expansion of HPC operations and constructions activities at the our HPC sites of $61.8 million as well as $1.4 million of bitcoin mining operations mainly related to miner repair costs.
    The following table presents selling, general and administrative expenses (in thousands):
    Three Months Ended September 30,Nine Months Ended September 30,
    2026202520262025
    Selling, general and administrative expenses$56,781$16,550$296,797$73,119
    Selling, general and administrative expenses – related party36812615,0567,989
    $57,149$16,676$311,853$81,108
    Selling, general and administrative expenses (including related party expenses) for the three months ended September 30, 2026 and 2025 were $57.1 million and $16.7 million, respectively, a net increase of $40.4 million.
    Selling, general and administrative expenses increased by $40.2 million during the three months ended September 30, 2026 as compared to the same period in the prior year primarily due to (i) a $25.7 million increase in stock-based compensation, (ii) a $9.0 million increase in employee compensation and benefits associated with increased employee base to support the Company’s long term growth strategy and (iii) a $2.1 million increase in information technology, legal and other professional fees.
    66

    Selling, general and administrative expenses (including related party expenses) for the nine months ended September 30, 2026 and 2025 were $311.9 million and $81.1 million, respectively, a net increase of $230.8 million.
    Selling, general and administrative expenses increased by $223.7 million during the nine months ended September 30, 2026 as compared to the same period in the prior year primarily due to (i) a $171.1 million increase in stock-based compensation, (ii) a $33.7 million increase in employee compensation and benefits associated with increased headcount following the acquisition of Beowulf E&D in May 2025 as well as larger employee base to support the Company’s long term growth strategy, and (iii) a $6.4 million increase in information technology, legal and other professional fees. In addition, selling, general and administrative expenses – related party increased $7.1 million during the nine months ended September 30, 2026 as compared to the same period in the prior year primarily due to a $14.4 million charitable contribution to The TeraWulf Charitable Foundation in the form of Common Stock, partially offset by costs incurred pursuant to the Services Agreement with Beowulf E&D during nine months ended September 30, 2025 prior to the acquisition of Beowulf E&D and the termination of the Services Agreement in May 2025.
    Depreciation for the three months ended September 30, 2026 and 2025 was $29.6 million and $26.5 million, respectively, an increase of $3.1 million. The increase was primarily due to an increase of $17.3 million related to HPC infrastructure constructed and placed in service at the Lake Mariner Data Campus partially offset by a decrease of $14.2 million related to miners and digital assets infrastructure taken out of service. Depreciation for the nine months ended September 30, 2026 and 2025 was $79.4 million and $60.9 million, respectively, an increase of $18.5 million. The increase was primarily due to an increase of $31.3 million related to HPC infrastructure constructed and placed in service at the Lake Mariner Data Campus partially offset by a decrease of $12.8 million related to miners and digital asset infrastructure taken out of service.
    Gain on fair value of digital assets, net during the three months ended September 30, 2026 and 2025 was $(0.6) million and $(0.3) million, respectively. Loss (gain) on fair value of digital assets, net during the nine months ended September 30, 2026 and 2025 was $0.9 million and $(0.4) million, respectively, due to the volatility and fluctuations in the price of bitcoin during the three and nine months ended September 30, 2026 as compared to the same periods in the prior year.
    Change in fair value of contingent consideration was $0 during the three and nine months ended September 30, 2026, as compared to $8.8 million and $10.4 million during the three and nine months ended September 30, 2025. The change in the three and nine months ended September 30, 2025 related to the fair value remeasurement of contingent consideration liabilities for the acquisition of Beowulf E&D which were fully settled during the year ended December 31, 2025 upon achievement of the related earnout milestones.
    Impairment of property, plant, and equipment was $9.7 million and $35.4 million during the three and nine months ended September 30, 2026. The $9.7 million impairment recorded during the three months ended September 30, 2026 related to the write down of certain miners due to expected lower recoverable values. The $35.4 million impairment recorded during the nine months ended September 30, 2026 included the write down of certain miners, and relating to the shutdown of a mining facility and the cessation of related bitcoin mining operations to support the Company’s transition to HPC operations. In addition, the Company recorded a $16.8 million impairment charge related to asset retirement costs assumed in connection with the Justified Data Campus acquisition. The Company assumed an asset retirement obligation as part of the acquisition and recorded the related asset retirement cost in property, plant and equipment, net. Because the related acquired assets were not expected to provide future economic benefit, the capitalized asset retirement cost was fully impaired during the nine months ended September 30, 2026.
    Loss on disposals of property, plant, and equipment was $3.9 million and $4.3 million during the three and nine months ended September 30, 2026 primarily related to a $3.4 million and $4.0 million loss on 5,010 and 5,370 miners sold or otherwise disposed of for proceeds of $0.4 million and $0.4 million, respectively. In addition, the Company recognized a net loss of $0.5 million and $0.3 million related to certain electrical equipment that were sold or otherwise disposed at the Justified Data Campus during the three and nine months ended September 30, 2026. Loss on disposals of property, plant, and equipment was $2.0 million and $5.8 million during the three and nine months ended September 30, 2025, related to 8,910 and 11,828 miners sold or otherwise disposed of for proceeds of $6.9 million and $8.8 million, respectively.
    Interest expense during the three months ended September 30, 2026 and 2025 was $53.6 million and $9.8 million, respectively, an increase of $43.8 million. The increase was primarily attributable to a $39.8 million increase in stated interest expense and a $2.9 million increase in the amortization of debt issuance costs associated with the 2030 Secured Notes and 2032 Convertible Notes issued during the fourth quarter of 2025 and the 2031 Convertible Notes issued in August 2025.
    67

    Interest expense during the nine months ended September 30, 2026 and 2025 was $177.0 million and $17.9 million, respectively, an increase of $159.1 million. The increase was primarily attributable to a $133.3 million increase in stated interest expense and a $24.8 million increase in amortization of debt issuance costs related to the 2030 Secured Notes and 2032 Convertible Notes which were issued during the fourth quarter in 2025 and 2031 Convertible Notes which was issued in August 2025.
    Change in fair value of warrant and derivative liabilities during the three and nine months ended September 30, 2026 was $728.4 million and $(243.6) million, respectively, related to the fair value of the Google Warrants driven by the fluctuation in the Company’s stock price during the respective periods. Change in fair value of warrant and derivative liabilities during the three and nine months ended September 30, 2025 was $(424.6) million related to (i) $(324.1) million for the change in the fair value of the Google Warrants and (ii) $(100.6) million for the conversion feature of the 2031 Convertible Notes which was originally accounted for separately as a derivative liability.
    The Company recognized no loss on extinguishment of debt during the three months ended September 30, 2026 and a $7.1 million loss during the nine months ended September 30, 2026, related to the full prepayment of the outstanding $100.0 million principal amount of the Bridge Credit Facility and the termination of the Bridge Credit Agreement. The early repayment resulted in a loss on extinguishment of debt of $7.1 million, representing the write-off of unamortized debt issuance costs.
    Interest income during the three months ended September 30, 2026 and 2025 was $28.6 million and $4.1 million, respectively, an increase of $24.5 million. Interest income during the nine months ended September 30, 2026 and 2025 was $86.9 million and $7.6 million, respectively, an increase of $79.3 million. These increases were primarily due to higher average cash balances during the periods.
    Other (loss) income, net was $(0.2) million and $0.7 million during the three and nine months ended September 30, 2026, consisting primarily of proceeds from the sale of scrap metal generated in connection with the Company’s construction activities as well as net losses on the restricted trust investments.
    Income tax provision was $28,000 and $84,000 for the three and nine months ended September 30, 2026, respectively. Based upon the level of historical U.S. losses and future projections over the period in which the net deferred tax assets are deductible, at this time, management believes it is more likely than not that the Company will not realize the benefits of the remaining deductible temporary differences, and as a result the Company has recorded a full valuation allowance against its net deferred tax assets as of September 30, 2026 and December 31, 2025, except for a $160,000 and $76,000 deferred tax liability as of September 30, 2026 and December 31, 2025, respectively, arising from indefinite-lived assets (e.g., tax-deductible goodwill related to the acquisition of Beowulf E&D) that cannot be used as a source of taxable income to support the realization of deferred tax assets when a full valuation allowance is in place.
    Equity in net loss of investee, net of tax was $0.5 million and $23.1 million for the three and nine months ended September 30, 2026, respectively, which represents TeraWulf’s proportional share of net loss of the Abernathy Joint Venture which was formed in October 2025 and has not yet commenced operations. On July 5, 2026, the Company sold its entire 50.1% interest in the Abernathy JV and recorded its equity in net loss of investee, net of tax through the period of its ownership during the three and nine months ended September 30, 2026.
    The Company recognized a $95.0 million gain on the sale of its equity interest in the Abernathy Joint Venture during the three and nine months ended September 30, 2026, resulting from the disposition of its entire 50.1% membership interest to the Fluidstack Member and certain other purchasers.
    Non-GAAP Measure
    To provide investors with additional information in connection with our results as determined in accordance with generally accepted accounting principles in the United States (“U.S. GAAP”), we disclose Adjusted EBITDA as a non-GAAP measure. This measure is not a financial measure calculated in accordance with U.S. GAAP, and it should not be considered as a substitute for net loss, operating loss, or any other measure calculated in accordance with U.S. GAAP, and may not be comparable to similarly titled measures reported by other companies.
    68

    We define Adjusted EBITDA as net income (loss) adjusted for (i) impacts of interest, taxes, depreciation and amortization; (ii) stock-based compensation expense, amortization of right-of-use asset, accretion of asset retirement obligations, related party expenses settled with respect to Common Stock and stock-based charitable contribution to The TeraWulf Charitable Foundation which are non-cash items that the Company believes are not reflective of its general business performance, and for which the accounting requires management judgment, and the resulting expenses could vary significantly in comparison to other companies; (iii) equity in net loss of investee, net of tax, related to the Abernathy Joint Venture and the gain on sale of equity interest in investee; (iv) interest income and other (loss) income, net for which management believes are not reflective of the Company’s ongoing operating activities; (v) change in fair value of warrant liabilities, changes in fair value of contingent consideration, loss on extinguishment of debt, loss on disposals of property, plant and equipment and impairment of property, plant and equipment which are not reflective of the Company’s general business performance; and (vi) acquisition-related transaction costs which management believes are not reflective of the Company’s ongoing operating activities.

    Loading holders...

    Held by

    holders ( registered funds via N-PORT, institutional investors via 13F). Showing top by dollar value.

    Holder Type ETF MF Position ($) % of holder Δ % of holder Holder AUM

    Recent insider activity

    Last 90 days. Open-market trades (purchases & sales) by directors, officers, and 10%+ owners. 3 transactions across 3 insiders. Net: -180,564 shares, -$2,885,785.

    Date Insider Role Action Shares Price Value
    2026-09-15 Bucella Michael C. Director Buy +6,085 $14.79 $89,967
    2026-09-08 Motz Catherine J. Director Sell -56,023 $17.81 -$997,943
    2026-08-31 Carter Walter E. Director Sell -130,626 $15.14 -$1,977,808

    Source: SEC Form 4 filings.

    Next expected filings

    • ~2027-02-26 10-K expected by 2027-03-11 (in 89 days)
    • ~2027-05-06 10-Q expected by 2027-05-09 (in 158 days)
    • ~2027-08-03 10-Q expected by 2027-08-06 (in 247 days)
    • ~2027-11-04 10-Q expected by 2027-11-07 (in 340 days)

    Predicted from historical filing cadence; not an SEC commitment.

    Recent SEC filings

    • 2026-11-06 8-K Earnings Release; Regulation FD Disclosure; Financial Statements and Exhibits
    • 2026-11-06 10-Q Quarterly Report
    • 2026-11-04 8-K Material Agreement Entered; Regulation FD Disclosure; Other Events; Financial Statements and Exhibits
    • 2026-10-23 8-K Material Agreement Entered; Material Financial Obligation
    • 2026-10-05 8-K Other Events; Financial Statements and Exhibits
    • 2026-08-05 8-K Earnings Release; Regulation FD Disclosure; Financial Statements and Exhibits
    • 2026-08-05 10-Q Quarterly Report
    • 2026-07-06 8-K Other Events; Financial Statements and Exhibits
    • 2026-05-26 8-K Other Events; Financial Statements and Exhibits
    • 2026-05-08 8-K Earnings Release; Regulation FD Disclosure; Financial Statements and Exhibits
    • 2026-05-08 10-Q Quarterly Report
    • 2026-04-28 DEF 14A Proxy Statement
    • 2026-04-16 424B5 Prospectus Supplement
    • 2026-04-16 8-K Material Agreement Entered; Other Events; Financial Statements and Exhibits
    • 2026-04-14 S-3ASR S-3ASR