Senate Approves Bipartisan Permitting Overhaul, Tightens Review Deadlines and Shifts Grid Costs to Big Power Users

·

The Senate has passed a bipartisan permitting and transmission overhaul that would speed federal reviews for major infrastructure and energy projects, tighten deadlines for agency decisions and lawsuits, and require large new electricity users such as data centers to shoulder more of the grid-upgrade costs tied to their demand.

The chamber approved H.R. 2347, as amended, by a 62-33 vote on Thursday, using the House bill as the vehicle for the Bipartisan American Affordability and Jobs Act of 2026, or BAAJA. A bipartisan manager’s substitute was adopted a day earlier, 69-27. The measure now goes to the House.

The bill would make broad changes across federal permitting law, including the National Environmental Policy Act, which governs environmental reviews; the Clean Water Act; the Endangered Species Act; the National Historic Preservation Act; and federal transmission policy and Federal Energy Regulatory Commission authorities.

In practical terms, the package is meant to force faster decisions on projects that often take years to clear federal review. Environmental assessments would generally have to be completed within one year, while more detailed environmental impact statements would face a two-year deadline. A record of decision would have to be issued within 45 days after an environmental impact statement is published. Some other federal authorizations would face 90-day deadlines, with 120 days for some agencies that did not participate in the review process.

The legislation also would narrow the time to challenge many project approvals in court. In most cases, claims would be barred unless filed within 150 days after the authorization is made public. Another provision aimed at “project certainty” would generally stop federal agencies from revoking, rescinding or materially changing certain permits already in effect on or after Nov. 6, 2026, except in limited circumstances such as a court order, fraud, a material breach or newly discovered imminent harms.

Another significant piece of the package addresses transmission and rising power demand from large computational loads, including data centers. Sponsors and coverage of the bill describe those provisions as requiring large new users to pay more of the grid-upgrade costs they cause, rather than passing those expenses on to other utility customers.

The issue matters well beyond Washington because permitting rules affect how quickly factories, transmission lines, power plants, pipelines and other large projects can be built. For manufacturers, utilities and developers, the debate is about cost, timing and whether permits can survive years of litigation after an agency decision.

The National Association of Manufacturers, a business lobbying group, applauded the Senate vote and said the current U.S. permitting system costs manufacturers more than $12 billion a year. The group estimated the bill could cut those costs by more than a third, saving more than $4 billion annually. Those figures are the group’s estimates.

Supporters cast the bill as a long-sought bipartisan effort to make it easier to build energy and industrial projects in the United States. Sen. Shelley Moore Capito, R-W.Va., one of the lead Senate negotiators, said in a statement: “I’m thankful for my colleagues’ efforts to strengthen this legislation, the contributions from members of the House, and the support of countless organizations from across the country. I urge the swift passage of BAAJA to make life more affordable for American families.”

The main Senate negotiators and sponsors were Capito; Sen. Mike Lee, R-Utah; Sen. Sheldon Whitehouse, D-R.I.; and Sen. Martin Heinrich, D-N.M.

Opposition has come from environmental and tribal-interest groups, which argue the bill would weaken environmental oversight, limit judicial review and undercut tribal and historic-preservation consultation. Jen Duggan, executive director of the Environmental Integrity Project, told The Associated Press: “Make no mistake: This backroom deal will pave the way for even more fossil fuel projects like gas power plants for data centers, oil and gas pipelines and (liquefied natural gas) terminals while sacrificing fundamental and common-sense public health and environmental protections for communities across the U.S.”

The bill is not yet law. To reach the president’s desk, it must pass the House in identical form and then be signed. The current Congress ends Jan. 3, 2027. If the House does not act by then, the legislation would need to be reintroduced in the next Congress.

Tags: #congress, #permitting, #energy, #datacenters