GAO Audit Says ICE’s Rapid Detention Expansion Risked Waste
A new federal audit says U.S. Immigration and Customs Enforcement’s recent detention expansion — backed by a $45 billion appropriation available through 2029 — was marked by rushed warehouse purchases and millions of dollars in payments for unused detention beds, creating a serious risk of waste.
The report, published Nov. 19 by the Government Accountability Office, Congress’ nonpartisan audit arm, is titled “Immigration Detention: ICE Should Determine Cost Effectiveness of New Initiatives Before Continuing.” It makes an important distinction: Congress did not find that ICE spent $45 billion in a single year. Instead, Public Law 119-21, enacted in July 2025, provided $45 billion for detention capacity for single adults and families, with the money available through Sept. 30, 2029. GAO said ICE had obligated about $9.1 billion of that detention funding through July 2026.
GAO tied the surge in spending authority to a January 2025 executive order directing the Department of Homeland Security to expand detention, followed by the July 4, 2025, enactment of the law that supplied the new money. The audit reviewed how ICE moved to carry out that expansion and whether the agency had adequately planned for the costs.
One major focus was a warehouse acquisition initiative that GAO said ICE launched quickly and without sufficient cost estimates. ICE bought 11 warehouses for about $1.07 billion. GAO found that nine of the 11 were purchased for at least 50% above local assessed values, and six were bought for at least double assessed value.
The agency later planned to sell seven of the 11 warehouses, the report said, raising the prospect that taxpayers could be left with losses on resale as well as sunk costs from the initial purchases. GAO’s conclusion was blunt: “the warehouse initiative is an example of a major investment that was implemented rapidly and will likely result in significant waste.”
GAO said the problem was not just the price tag but the lack of analysis behind it. The audit found ICE did not develop sufficient life-cycle cost estimates — meaning projections of what an asset will cost over its full useful life, not just at purchase — or cost-effectiveness analyses before making the investments. “Lacking these life-cycle cost estimates, ICE will likely continue to make investment decisions with limited information and risk overpaying for these acquisitions,” GAO said.
The audit also examined detention contracts that guarantee operators a minimum level of payment whether beds are filled or not. Across five selected facilities, GAO estimated ICE was paying about $13,032,520 per month for empty beds, based on average occupancy from October 2025 through April 2026. At the Folkston, Georgia, facility known as Folkston (D. Ray), GAO estimated ICE paid about $540,047 per month for empty beds during that period.
Those findings do not mean all detention spending was wasteful, and GAO did not say the full $45 billion appropriation was misspent. But the report repeatedly faulted ICE for moving ahead on major investments before determining whether the plans were cost effective.
GAO recommended that ICE update its detention spending plans and develop life-cycle cost estimates and alternatives analyses before continuing major acquisitions. According to the report, DHS and ICE concurred with the recommendations.
The audit leaves ICE with a large, still-available pool of detention funding and a clear warning from Congress’ oversight arm: before the agency expands further, it should show that its plans are financially sound.